NOTE:
Make sure the indicator light of overload reset
button(or output indicator) is green on each inverter.
6. The low idle switch(button) must be in the same
position (ON or OFF) on both generators before
applying any load.
7. Plug in the 240 Volt AC, single phase, 60Hz electrical
loads into parallel kit receptacles and turn on first
load. Allow generator output to stabilize before
plugging in the next load.
NOTE :
It is strongly recommended to plug in devices
with the largest output first and the smallest output
last to help prevent overloading the inverters. Do not
exceed maximum wattage rating of inverters, parallel
kit and receptacles.
8.When finished, turn off the inverter generators
per owner’s manual instructions and then disconnect
the parallel kit.
ASSEMBLY AND OPERATION
4
5c. Remote start
Turn and hold the REMOTE START switch for 5
seconds until the engine start.
Summary of Contents for PK12000
Page 13: ...Fontana CA 92337 USA Phone 855 888 3598 support a ipower com www a ipower com ...
Page 26: ...Fontana CA 92337 EE UU Teléfono 855 888 3598 support a ipower com www a ipower com ...
Page 39: ......
Page 40: ...Fontana CA 92337 USA Téléphone 855 888 3598 support a ipower com www a ipower com ...