![3M QT-III Quick Start Manual Download Page 8](http://html1.mh-extra.com/html/3m/qt-iii/qt-iii_quick-start-manual_3261224008.webp)
8
78-8126-9537-3-B
5.0 Install Termination
5.1 Select the large hi-K mastic pad from the kit. Remove the liners and align the pad with 1" (25 mm) covering the
semi-con, and 5" (127 mm) covering the cable insulation. Using light tension, wrap the pad around the cable
insulation two times. Trim the pad to overlap the start by approximately 0.25" (6 mm). Taper the pad edge by
gently pressing along the edge with your finger. (
Figure 9
)
3EMI#ON
4APER%DGE
#ABLE)NSULATION
#ABLE)NSULATION
(I+-ASTIC0AD
(I+-ASTIC0AD
,AYERS
MM
MM
Figure 9
5.2 Wrap two half-lapped layers of highly-tensioned Scotch® Vinyl Electrical Tape Super 88 over the hi-K mastic
pad, leaving approximately 0.125" (3 mm) of mastic exposed at each end. Taper the exposed edges of the hi-K
mastic onto the cable by gently pressing along the edge with your finger. (
Figure 10
)
3EMI#ON
#ABLE)NSULATION
6INYL
4APE
4APER%DGEOF
(I+-ASTIC
4APER%DGEOF
(I+-ASTIC
MM
MM
Figure 10