Z1471

ASSEMBLY INSTRUCTIONS FOR PIPE CLAMP HARDWARE

WARNING

: Cancer and Reproductive Harm - 

www.P65Warnings.ca.gov

ADVERTENCIA: 

Cáncer y daño reproductivo - 

www.P65Warnings.ca.gov

AVERTISSEMENT: 

Cancer et effets néfastes sur la reproduction - 

www.P65Warnings.ca.gov

Z1471 PIPE CLAMP HARDWARE

1.

Assemble the two anchor bars (with formed offsets towards spade bolt) to spade bolt using:

(1)

1/4-20 NC x 3/4 [19] Long Machine Screw

(1)

1/4-20 NC Nut

(2)

1/4 [6] Flat Washers

Place a 1/4 [6] flat washer on each side of spade bolt, then place an anchor bar on each side of the 1/4 [6] flat washer
(A 1/4 [6] flat washer goes between the spade bolt and anchor bar on each side).  Place the 1/4-20 NC x 3/4 [19] long
machine screw through the entire assembly and thread on the 1/4-20 NC nut.

Note that the 1/4-20 NC machine screw and nut holding the anchor bars (in an "x" configuration) to the spade bolt should
not be tightened.  The nut should be run onto the machine screw until 4 or 5 threads of the machine screw are past the
nut.

2.

Slide the adjusting bar onto the threaded end of the spade bolt.

3.

Thread the 3/8-16 NC nut onto the threaded end of the spade bolt in front of the adjusting bar.

4.

DO NOT attach the strainer and strainer attachment nut, these will be used at final installation (see page 2).
The assembly is ready to be installed in pipe.