ZXSDR BS8900A Hardware Installation
Context
On-site engineering personnel need to install the ground PE cable from the outdoor
grounding bar to the bus bar of the baseband cabinet to protect the ZXSDR BS8900A.
The fan subrack,
BBU
subrack, and
LPU
grounding cable of the baseband cabinet are
already installed. Engineering personnel need to verify that the cables are securely fixed.
Steps
1.
Remove the cover of the left-side routing trough and the front baffle of the base.
2.
Route the grounding cable along the left-side waterproof module of the baseband
cabinet and the left-side routing trough of the RF cabinet, and connect the cable to
the grounding copper bar of the baseband cabinet, see
Figure 7-12
. Prepare the
grounding cable of a particular length in accordance with the distance between the
baseband cabinet and the grounding copper bar.
7-14
SJ-20150203110107-011|2016-03-23 (R1.1)