Zoeller 810 Скачать руководство пользователя страница 6

6

© Copyright 2017 Zoeller

®

 Co. All rights reserved.

  1.  Review the drawing in Fig. 4 on page 5 and the actual system to become familiar 

with the components in the packaged grinder pump system.  Review where the unit 

will be installed.  Determine where the power feed, inlet pipe, and discharge pipe will 

be located.

  2.  Remove the unit from packing.  Prepackaged outdoor systems are preassembled at 

the Zoeller Company and require a minimum of field assembly work.  Float switches 

are set and tethered for proper operation from the Factory.  The alarm switch should 

be located 5 cm (2”) above the pump “on” level.

  3.  Float switches are tied in place for shipping purposes on all model prepackaged 

systems.  Cut the cable tie around each float switch bulb or the unit will not operate 

properly.  Verify that where the float switches are set will work for your application.  

Verifying that the float switches are set properly and will not hang up inside 

the basin is the responsibility of the installing contractor. 

  4.  Dig a hole for the basin.  The hole should be at least 61 cm (24”) larger in diameter 

than the basin diameter to provide 30 cm (12”) of backfill all around and deep enough 

to provide either 30 cm (12”) of compacted backfill or 16 cm (6”) when a concrete pad 

is required.  Ensure the removable cover extends above the finished grade line and 

the grade slopes away from the unit.  Backfill and subbase should be 3 mm (1/8”) – 

19 mm (3/4”) pea gravel or 3 mm (1/8”) – 13 mm (1/2”) crushed stone.  (Reference 

basin installation instructions included with unit)

 

5.

  Note:  Care must be taken when excavating in order to avoid underground 

utilities and disturbance of existing structure foundations.  The hole should 

be located at least ten feet from adjacent structures.  Additional distance may 

be required to sufficiently locate the basin outside of the loading area of the 

adjacent structures.

  6.  The location of the inlet fitting is determined by the depth of the inlet pipe.  The inlet 

fitting must be used with 10 cm (4”) pipe.  It is best to install the inlet on the side of 

the basin opposite the float switches.  To install, use a 13 cm (5”) hole saw to drill 

into the side of the basin at the correct elevation.    Center the hub inner diameter 

with the hole in the basin.  Attach the hub to the side of the basin using the sealant 

and hardware provided.

  7.  The bottom of the excavation can now be back filled and compacted.  Set basin in 

hole and connect the 10 cm (4”) inlet pipe to the inlet hub.  

  8.  The discharge piping is connected to the 3 cm (1-1/4”) threaded fitting located in 

the basin sidewall.

  9.  On basin depths of 182 cm (72”) and greater, the system’s disconnect assembly 

is shipped loose and must be screwed into the discharge piping. Apply pipe dope 

to threaded connection.

  10.  Connect pull rod to Pump assembly.  Connect lift cable to top of pump.  Lower the 

pump into basin ensuring the discharge pipe bracket slides into the disconnect 

fitting.

  11.  Pouring a concrete anchor around system can now be completed.   Basin should 

be filled with water when pouring concrete to minimize movement of the system.  

Back fill around basin with specified media.  Care should be used to avoid damaging 

components or leaving voids when back filling.  Refer to Basin installation reference 

guide on more specific requirements.

 12.

  Note: The progressing cavity grinder basin is a sewage holding tank.  Vent 

connection should be installed in accordance with all national, state and local 

plumbing codes.

  

  13.  Dig a trench for the electrical conduit.  Trench should be located at least 45 cm (18”) 

deep and follow all applicable NEC codes.  Connect electrical wiring to Junction 

box according to wiring instructions included in this manual and wiring diagram in 

box.  Use the included sealant when closing Junction box.

  14.  If used, a control panel is installed within sight of the system.  Connect float switches 

and pump cords according to the “Pump Wiring Instructions” found in this manual 

and located inside the panel enclosure.

  15.  Remove any debris from the basin.  Using clean water, check the system for proper 

operation.

  16.  Seal and secure the lid using the proper bolts and sealant when using a lid without 

a formed gasket. 

  17.  Add water to the basin and test the system for leaks and proper pump operation.

  18.  Record system start up data for future reference.

Outdoor Prepackaged System Installation Instructions

This set of instructions is for factory prepackaged outdoor progressing cavity grinder systems only.  If this is a field assembled outdoor system you can 

use these instructions as a guideline.

GENERAL

Zoeller pumps are lubricated and tested at the factory prior to shipment and require 

minimum pre-start-up maintenance.

Maximum operating temperature of pumped liquid for standard model pumps must not 

exceed 54 °C (130 °F) for 60Hz units, 40 °C (104 °F) for 50Hz units.

These units are not designed to handle liquids other than sanitary sewage. If pump is 

used to dewater areas with contaminated liquids with heavy or abrasive materials, the 

warranty will be voided.

NAMEPLATE DATA

The nameplate, located on the top of the pump, indicates specific information about 

the construction of the pump. The model number and date code information should be 

recorded on the front page in the “Owner’s Information” section of this manual.

SHORT-TERM STORAGE

When not in use, the pump should be stored and the following is advised:

•  Drain pump housing by laying pump horizontal with discharge down. Then stand pump 

on legs.

•  Store pump inside whenever possible or cover with some type of protective covering.

•  Tape or seal in plastic bag the terminal ends of wire leads.

Operation

SK2533

6-5/8” (143 mm)

8-3/8”

(213 mm) 

5-1/4”

(133 mm)

4-3/8”

(111 mm)

10-1/2”
(267 mm)
DIA.

22-3/8” (568 mm)

4” (103 mm)

FIG. 5

POSITIVE DISPLACEMENT

GRINDER PUMP

1-1/4" NPT

ANTI-SIPHON VALVE

DN32 (1-1/4") 

DISCHARGE LINE

1-1/4" NPT CHECK VALVE

DISCONNECT

DN32 (1-1/4") SHUT OFF VALVE

(HOME OWNER)

(JWA)

CURB/VALVE

BOX

CHECK VALVE

SHUT OFF

VALVE

MAIN

OPTIONAL LOCATION 1-1/4"

NPT ANTI-SIPHON VALVE

FIG. 5A

SK2810

Содержание 810

Страница 1: ... serious personal injury death or major property damage Warns of hazards that CAN cause serious personal injury death or major property damage Warns of hazards that CAN cause personal injury or property damage INDICATESSPECIALINSTRUCTIONSWHICHARE VERY IMPORTANT AND MUST BE FOLLOWED THOROUGHLY REVIEW ALL INSTRUCTIONS AND WARNINGS PRIOR TO PERFORMING ANY WORK ON THIS PUMP MAINTAIN ALL SAFETY DECALS ...

Страница 2: ...ld be taken that the tethered float switch will not hang up on the pump apparatus or pit peculiarities and is secured so that the pump will shut off It is recommended to use rigid piping and fittings and the pit be 45 cm 18 or larger in diameter 3 Pump should be checked frequently for debris and or build up which may interfere with the float on or off position Repair and service should be performe...

Страница 3: ...Prepackaged Systems Field Assembled Systems are discussed on page 4 4 Zoeller 810 and 815 Grinder Pumps can be retrofitted to existing positive displacement pump installations Applications FIG 1 2 CONSULT FACTORY FOR INTERMITTENT USE ABOVE 73 METERSTOTAL DYNAMIC HEAD MAXIMUM PUMP OUTPUT 80 METERS 0 5 10 PUMP PERFORMANCE CURVE MODEL 815 50 Hz 1 0 1 5 2 0 2 5 3 0 20 30 40 50 60 70 80 0 L sec m hr 3 ...

Страница 4: ...emoving the cover Start and run winding resistance can only be measured after removing the cover and checking at the through wall terminals General Information PROGRESSING CAVITY GRINDER PUMP DESCRIPTION 1 Pumps are constructed of class 30 cast iron protected with powder coated epoxy for long life when pumping sewage in submersible applications The cutter assembly is comprised of stainless steel c...

Страница 5: ...MP CONTROL FLOAT FLOAT TREE SK2540 PIPE SEAL FIELD INSTALLED 60 9 cm 24 MIN DN100 4 RUBBER INLET HIGH WATER ALARM NOT INCLUDED 213 cm 84 183 cm 72 152 cm 60 SOLID FIBERGLASS COVER FIBERGLASS ANTI FLOTATION FLANGE DISCHARGE FITTING 1 1 4 BULK HEAD CHECK VALVE 1 1 4 FEMALE NPT DISCHARGE PIPE 1 1 4 GALVANIZED WATERTIGHT QWIK BOX DN50 2 PVC ELECTRICAL PIPE DN32 1 1 4 PVC SLIP X SLIP FIBERGLASS BASIN B...

Страница 6: ...acket slides into the disconnect fitting 11 Pouring a concrete anchor around system can now be completed Basin should be filled with water when pouring concrete to minimize movement of the system Backfillaroundbasinwithspecifiedmedia Careshouldbeusedtoavoiddamaging componentsorleavingvoidswhenbackfilling RefertoBasininstallationreference guide on more specific requirements 12 Note The progressing ...

Страница 7: ...30 kg 67 in lbs Replace star cutter with the correct shims Install washer and torque hex head bolt to 23 kg 71 in lbs 34 kg 75 in lbs apply Loctite 262 thread lock sealant or equal to bolt threads prior to insertion Check running clearance withpumpinverticalpositiontoremoveendplay Clearance must be between 0 178 mm 0 007 and 0 305 mm 0 012 to obtain efficient grinding when pump is put back in serv...

Страница 8: ...uld be performed by a Zoeller Pump Company Authorized Service Station only SAFETY PROCEDURES For your protection always disconnect pump and panel from its power source before handling Never enter the basin until it has been properly vented and tested Any person entering a basin should be wearing aharnesswithsafetyropeextendingtothesurfacesothattheycan be pulled out in case of asphyxiation Sewage w...

Отзывы: