7
Start-up
7.1
General information
For details of commissioning the ZAdyn4C, refer to the
“
Commissioning
”
chapter in the ZAdyn4C
operating instructions.
If the absolute value encoder cable length is greater than 5 m, the operating voltage of the absolute
value encoder has to be checked.
Operating voltage
Consequence
3.6 - 14 VDC
Absolute value encoder can be used.
4.75 - 5.25 VDC
Absolute encoder must be replaced with an abso-
lute encoder with an operating voltage of 3.6 - 14
VDC.
8
Con
fi
guring the ZAdyn4C
There are two processes for con
fi
guring the ZAdynpro:
•
Manual setting of the parameter values
•
Loading parameters onto the ZAdyn4C
8.1
Manual setting of the parameter values
Enter the parameter values in the following parameter list (see "Saving the parameter values of the
ZETADYN 3C" chapter). After mechanical and electrical installation, you can transfer the parameter
values to the ZAdyn4C.
Technical Information
Start-up
R-TIA19_02-D-GB 1942
Part.-No. 00163469-D-GB
18/26