STANDARD OPERATING PROCEDURE 
String Inverter Installation – Zeverlution Series 

 

Version 1.2 Effective date 02/08/2017

 

 

Page 10 of 15 

2.

 

Connect the module leads to the short 
input leads of the TS4-R-O unit. 

 

3.

 

Connected the long output leads of the optimiser to the output leads of the next optimiser. 

 

 
Secure any wiring loops and loose cables to the module frame or the mounting rails. All optimisers 
come with genuine MC4s and so do the modules. If you find non-genuine connectors on either the 
module or the optimisers, please contact solarcity immediately. The optimiser’s output leads have 
a length of 1000mm which is usually too short for leapfrog wiring. Please use standard daisy chain 
wiring for all optimised array sections. 
 

5.3.3

 

AC Wiring  

 

The inverter is connected to the switchboard using double insulated 3-core cable (2C+E). Circular 
TPS should be used to connect the inverter to the AC isolator. Standard TPS cable can be used 
for the cable run between switchboard and AC isolator. If no AC isolator is required, use circular 
TPS all the way from the inverter to the switchboard. External AC cabling must be run in UV 
resistant HD conduit (with the Solar T labelling hidden since it is AC not DC). 

 

The table below shows the conductor cross section and maximum cable length for each inverter.  

 

 

 

2.5mm²

4mm²

6mm²

Zeverlution 2000s

15m

25m

40m

Zeverlution 4000

n/a

15m

20m

max. cable length 

conductor cross-section 

Содержание Zeverlution Series

Страница 1: ...2 BEHAVIOURAL 2 SAFETY 2 INSTALLATION PROCEDURE 3 String Design Guidelines 3 5 1 1 String Layout Without Optimisers 3 5 1 2 String Layout with Optimisers 3 5 1 3 Shading 3 5 1 4 Maximum String Voltage...

Страница 2: ...d electrical part of the inverter installation instruction The focus of this SOP lies on the physical installation of Zeverlution 2000s and Zeverlution 4000 inverters and any associated switch gear DC...

Страница 3: ...4000 inverters and for arrays with or without optimisers the minimum and maximum strings lengths are as follows minimum number of modules per string is 3 maximum number of modules per string is 10 5 1...

Страница 4: ...systems with a peak output between 1 5kWp and 3kWp 6 to 10 modules where the peak performance rating per panel at STC does not exceed 295Wp For further details please refer to the Zeverlution 2000s da...

Страница 5: ...et which is used to fix the units to a suitable wall Please refer to the solarcity wall cladding guide for suitable wall claddings to mount the inverter on 1 Use the wall bracket as a drilling templat...

Страница 6: ...ble The inverter must not be installed in a location where it is exposed to direct sunlight Wiring 5 3 1 DC Wiring All wiring must be installed and sized in accordance with the relevant requirements o...

Страница 7: ...ted as per AS5033 The table below shows the maximum cable length one way between array and inverter with JA 290W panels allowing for a 2 voltage drop Panels per string 3 4 5 6 7 8 9 10 Max cable lengt...

Страница 8: ...to maintain the correct polarity the connectors are also marked with and symbols The steps below explain how to assemble SUNCLIX connectors Ensure that the array cable is de energized before installin...

Страница 9: ...lled on an appropriate roof penetration kit must be used Roof penetrations must always be located under the solar panels where an attic space is accessible for the cable run Where cable s pass through...

Страница 10: ...mm which is usually too short for leapfrog wiring Please use standard daisy chain wiring for all optimised array sections 5 3 3 AC Wiring The inverter is connected to the switchboard using double insu...

Страница 11: ...S 5033 2014 and follow the instructions outlined in the standard Attached to this document you ll find a commissioning sheet which you may use to record the test results A completed and signed copy of...

Страница 12: ...To confirm wait for approximately 10 seconds until the inverter automatically returns to the initial display showing the error code Connecting the inverter to the Internet The inverter needs to be co...

Страница 13: ...before setting up the WIFI connection 2 With the inverter powered up use a smartphone or laptop to search for the inverter s wireless access point This will display as ZEVERSOLAR XXXX Connect to this...

Страница 14: ...omer s wireless network 6 After approximately one minute the inverter should connect to the customers wifi network and the status indicator on the wireless page will show a green tick 7 Take a photo o...

Страница 15: ...rnet cable through the comms gland on the bottom of the inverter ensuring that the cable entry is sealed from dust and moisture 3 The inverter automatically obtains an IP address from the router via D...

Страница 16: ...rod MEN link removed Earth continuity 2 Main earth conductor to array frame Polarity check and PV open circuit voltage Polarity Voltage V String 1 String 2 if applicable PV array at switch disconnect...

Отзывы: