24 • Plumbing
PLUMBING
Dual Evaporation Pan Set Up
2 condensate evaporation pans will be installed in series on top of a Hybrid
™
configuration of an 8' or 12' Reveal Merchandiser
®
. The
evaporation pans and tubing should be installed before setting and shimming the case in order to access the back of the case.
1. Set the condensate evaporation pans on top of the case in the orientation shown.
2.
Locate the vinyl tubing shipped inside the display case. There will be a primary tube (16' long) and an overflow line (6' long). The
primary tube is connected between the condensate pump and the primary evaporation pan. The overflow line is connected between the
evaporation pans.
3. attach the primary tube to the back of the case using the supplied P-clips and screws. Route enough tubing under the case to connect to
the condensate pump, which will be mounted to the front of the case.
4. Insert the U-shaped copper pipe into the top of the discharge line and fasten together with the wire clamp. Hang the U-shaped copper pipe
over the edge of one of the evaporation pans. This will be the "primary" evaporation pan. Either evaporation pan can act as the primary
evaporation pan.
5.
Attach the overflow line from the tubing port (also called an "overflow exit") of the primary pan to the tubing port of the secondary pan.
Note: The entire length of the overflow line must stay below the top of the evaporation pans, and the tubing must not be kinked
or pinched as this will prevent water flow.
6. Plug the evaporation pans into a power source provided by the store.
DR-821-F
1 1/2"
End Panel
Condensate
Evaporation
Pans
Tubing
Ports
Electrical
Box
Support Braces
Condensing
Unit
Air Flow
Condensate Pump
Top of Reveal
™
Hybrid
™
Layout
Dual Evaporation Pan Orientation
(From Front of Case)
Overflow Line
(From Back of Case)
Overflow line connects the
tubing ports of each evap pan.
Parts Required:
Condensate evaporation pans
Screws & P-Clips
U-Shaped Copper Pipe
Vinyl Tubing