Parameterisation of boost ventilation and absent operating modes
As described in “3.1.6 Description of the operating functions and signals”, the boost ventilation and absent operation modes
can be adjusted according to user-specific needs.
NOTE
Parameterisation must be carried out in the accessible status of the control board.
Configuration of the boost ventilation mode
The temporarily active fan speed 4 operates as the boost ventilation function. To enable boost ventilation mode, DIP switch
no. 3 in MODE SW1 must be set to the ON position.
DIP switch no.
Position of DIP switch
3 ON
The boost ventilation time can be parameterised between 5 and 120 minutes with the programming module.
Configuration of the Away mode
The temporarily activated fan speed 1 operates as the Away function. The active operating time of fan speed 1 can be
parameterised between 15 and 59 min/h with the programming module.
Installing the exterior wall panel as a facade finish
WARNING
Danger due to falling exterior wall panel
The exterior wall panel is to be fixed using the supplied mounting accessories or with mounting material suitable for the
facade construction. The professional and safe installation is to be checked and the responsibility of the technical crew
performing the work.
NOTE
The exterior wall panel should not be installed until the façade is completed, however, immediately following installation
of the ventilation unit. Check the flatness between the wall mounting pipe, the EPP pipe housing, and the façade surface.
The connection between the wall mounting pipe and the facade surface must be permanently sealed against moisture
ingress.
Proceed as follows for the installation of the exterior wall panel:
1. Take the top cover of the outside wall panel off the bottom cover of outer cover as set out in 3.3.1.1, item 2.
NOTE
Using the raised contours for the airflow, put the bottom cover of the
outside wall panel onto the EPP housing section pipe extension so
that it fits exactly, and transfer the drill holes onto the façade
centrally.
Take the bottom cover of the outside wall panel off again and
prepare a suitable fastening technique for the four fixing points as
set out in the façade design.
NOTE
for the square wall mounting pipe
Use a hammer to cautiously tap in the respective driven-in dowel
into the four receiving holes in the EPP housing for the wall
mounting pipe surface plan.