User Manual 3PH HYD5000-HYD20000-ZSS
Rev. 1.1 16/03/2021
Identification: MD-AL-GI-00
Rev. 1. of 16/03/2021 - Application: GID
18/138
Consider the weight of the 3PH HYD5000-HYD20000-ZSS when
transporting and moving the inverters. Choose an appropriate
mounting position and surface. Assign at least two people to install the
inverter
Attention
The packaging materials and components can be damaged during transport. Therefore, check the
outer packaging before installation; check that the materials are not damaged. In case of damage,
contact the dealer as soon as possible.
It is recommended to remove the packing materials within 24 hours before installing the inverter.
3.4.
Installation tools
No.
Tool
Model
Function
1
Drill
(recommended: 6mm drill bit)
To make a hole in the wall
2
Screwdriver
To screw in the electrical
circuits
3
Star screwdriver
To remove the AC
terminal screws
4
Removal wrench
To remove the PV
terminals
5
Wire stripper
To strip the wires