3. Note on dismantling the scaffold tower

 

To dismantle the scaffold tower, follow the steps for assembly in reverse order. Before commencing 

dismantling, ensure that the necessary platforms or scaffold planks are installed again and laid flat 

for personnel to stand on. No part of the scaffold tower (braces, platforms etc.) may be removed before 

the levels above have been completely dismantled. 

4. Usage regulations 

1.  

Personnel must always climb to the work platform from 

the inside of the tower. 

2.   Personnel are prohibited to brace themselves against the 

side protection while working.

3.  Jumping on the platforms is prohibited. 

4.   Horizontal loads which could cause the scaffold tower to tip over must not 

be generated, e. g. as a result of working on adjacent constructions.

 

5.   Particular attention must be paid to wind conditions which might cause the scaffold tower to 

tip over when it is used in buildings open to the passage of wind, in uncovered buildings or at 

the corners of buildings. 

6.  Using ladders, crates or similar means to increase the height of the platform is prohibited. 

7.   Tools and materials may only be handed upwards. Always take the weight of tools and 

materials into consideration to avoid overloading the work platform. The person handing 

the load upwards must not let go of it until the person receiving it has a firm hold on it. 

8.   Scaffold  towers  with  swivel  castors  can  be  moved  to  their  final  location  after  assembly 

(the  ground  or  floor  must  not  slope  by  more  than  3  %).  Any  impact  must  be  avoided. 

When the scaffold tower is in its final position, the alignment must be checked again. 

9.  When moving the scaffold tower, always take care that it does not touch any live equipment.

10.   Electrical tools (drills etc.) may only be operated on the scaffold tower at Safety Extra Low 

Voltage (48 V), with protective insulation (separation transformer) or if they are connected 

with a ground fault circuit interrupter with a residual current of 30 mA. The stipulations of 

BGI 594 (formerly ZH 1/228) must be complied with. 

11.  Tools and materials must be stored on the work platform in such a way that there is 

a passageway of 20 cm at the sides of the work platform.

Содержание Skymaste Industrial Z600

Страница 1: ...Assembly and usage instructions www zarges de Z600 brace free mobile scaf fold towers...

Страница 2: ......

Страница 3: ...the scaffold tower 8 2 3 Other applicable safety instructions 8 2 4 Technical data 8 2 5 General assembly regulations 8 2 6 Basic dimensions 12 2 7 Identification 13 2 8 Parts list incl ballast see al...

Страница 4: ...rges de 82360 Weilheim Internet http www zarges de 1 3 Type approval All single parts are tested by T V Product Service The all in one scaffold towers listed here are tested for structural stability 1...

Страница 5: ...the conditions described above will result in liability for damages 1 7 Intended use The scaffold towers listed in these assembly and usage instructions may only be used as scaffold towers in accorda...

Страница 6: ...tower is not permissible 7 The first platform must not be more than 4 40 m above floor level The distance between further platforms must not exceed 4 m The platforms must be at least 1 70 m apart 8 W...

Страница 7: ...ce on which the scaffold tower is moved must be capable of bearing its weight 19 Where the scaffold tower is used outdoors or in open buildings it must be moved to a wind sheltered position or secured...

Страница 8: ...uction Instructions for handling work and safety scaffolds BGR 165 and BGI 594 formerly ZH 1 228 Safety rules for the use of electrical equipment in the case of increased electrical hazard apply when...

Страница 9: ...l to ensure that all stabilisers have contact with the ground Fig 3 Fig 4 5 Fit the platform diagonals Always attach the two platform diagonals directly above the 4th rung from the bottom The platform...

Страница 10: ...4 Fig 15 1 2 3 max 0 5m 10 Fit guard rail frame topmost platform Fig 17 9 Fit railings to rest platform only on scaffold towers with a working height exceeding 7 60m Fig 16 7 Align the scaffold tower...

Страница 11: ...tower please check again that it is aligned horizontally and that all four stabilisers have ground contact as this is essential for stability Fig 21 11 Fit railings to work plat form Remove auxiliary...

Страница 12: ...mobile scaffold towers 12 2 6 Basic dimensions Width 0 75m 1 35m Length 1 8m 2 5m 3 0m 1 8m 2 5m 3 0m a 1 8m 2 5m 3 0 1 8m 2 5m 3m b 0 75m 0 75m 0 75m 1 35m 1 35m 1 35m c 2 5m 2 5m 2 5m 3 25m 3 25m 3...

Страница 13: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 13 Z600 2 7 Identification Art No Type plate max platform height max perm load EAN code...

Страница 14: ...6 2 4 2 2 2 8 2 4 4 1 1 7 10 40 52080 8 2 4 2 2 2 8 2 4 4 1 1 X approx m Order No 42905 42904 42906 42956 42910 42913 42914 42908 42979 42926 42917 42940 42912 0 75 x 2 5 5 80 52130 2 2 2 2 1 2 2 2 2...

Страница 15: ...4 1 0 2 9 55 52370 2 6 2 4 2 2 2 2 8 2 4 4 1 0 3 10 40 52380 8 2 4 2 2 2 2 8 2 4 4 1 0 X approx m Order No 42902 42901 42903 42956 42910 42930 42911 42914 42908 42979 42926 42917 42940 42912 1 35 x 2...

Страница 16: ...e free mobile scaffold towers 16 2 9 Position of the single parts Stirrup step Trapdoor platform End toeboard Side toeboard Diagonal brace Stabiliser Railing Push on end frame 2 m Push on end frame 1...

Страница 17: ...height 5 45m Platform height 4 45m Weight 141 2kg Order No 52140 Scaffold size 0 75x2 50m Working height 6 45m Scaffold height 5 45m Platform height 4 45m Weight 152 1kg Order No 52240 Scaffold size...

Страница 18: ...Scaffold height 8 55m Platform height 7 55m Weight 196 6kg Order No 52170 Scaffold size 0 75x2 50m Working height 9 55m Scaffold height 8 55m Platform height 7 55m Weight 215 8kg Order No 52270 Scaffo...

Страница 19: ...45m Scaffold height 5 45m Platform height 4 45m Weight 170 5kg Order No 52440 Scaffold size 1 35x2 50m Working height 6 45m Scaffold height 5 45m Platform height 4 45m Weight 186 2kg Order No 52540 Sc...

Страница 20: ...Scaffold height 8 55m Platform height 7 55m Weight 249 0kg Order No 52470 Scaffold size 1 35x2 50m Working height 9 55m Scaffold height 8 55m Platform height 7 55m Weight 277 8kg Order No 52570 Scaffo...

Страница 21: ...the corners of buildings 6 Using ladders crates or similar means to increase the height of the platform is prohibited 7 Tools and materials may only be handed upwards Always take the weight of tools a...

Страница 22: ...ed in such a way that they are protected from the elements During transport to and from the place of storage the scaffold tower components must be secured to prevent sliding and impact The scaffold to...

Страница 23: ...easily Check the fail safe device wing bolt locking pin on the chassis beams and basic frame Stop springs Check for warping crushing cracks and correct seating If you require further information or i...

Страница 24: ...Push on end frame normal 0 75 m x 1 12 m 42905 0 75 m x 1 96 m 42904 Push on end frame wide 1 35 m x 1 12 m 42902 1 35 m x 1 96 m 42901 Diagonal brace 1 80 m 42937 2 50 m 42908 3 00 m 42938 Platform d...

Страница 25: ...Z600 Railings 1 80 m 42955 2 50 m 42956 3 00 m 42957 Guard rail frame 0 75 m 42906 1 35 m 42903 Trapdoor platform 1 80 m 42931 2 50 m 42910 3 00 m 42933 Platform without trapdoor 1 80 m 42932 2 50 m...

Страница 26: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 26 End toeboard 0 75 m 42913 1 35 m 42911 Side toeboard 1 80 m 42943 2 50 m 42914 3 00 m 42944 Stirrup step 0 40 m 42940...

Страница 27: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 27 Z600 7 Accessories Ballast weight 10 kg 42912 Wall anchor 0 90 m 42920...

Страница 28: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 28 NOTES...

Страница 29: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 29 Z600 NOTES...

Страница 30: ...Assembly and usage instructions Z600 brace free mobile scaffold towers 30 NOTES...

Страница 31: ......

Страница 32: ...No 291304 No 5021722 v0109...

Отзывы: