ALL SYSTEMS ARE SUPPLIED WITH A NEW FORESTAY. TYPICALLY 
THIS WILL HAVE A RIGGING SCREW AT THE BASE. 
 

Establish the length of the forestay before determining the foil length. This can be 
done by calculation or by trial installation of the forestay on the mast etc.. Do not 
swage the lower terminal on the Forestay until assembly of the Furling System is 
complete. 
 
 

NB

  In all cases the Forestay Rigging Screw MUST be compatible with the Furling 

Drum  and must have the special double hole toggle fitted to the lower end. (see 
drawing FS-1).  
 
 

 

Assembly of the Luff Foil

 

 
The length of the foil required can be determined by reference to our technical sheet. The 
foil length must be trimmed from the top as the bottom end has a machined sail entry slot 
and it is essential that its position relative to the lower end of the foil be maintained. 
 
If the luff foil (6) is not supplied in one complete section, connect the aluminium sections 
that make up the foil using the Foil Connector Sleeves (17) and  socket set screws m6x8 
(16). Use Loctite 638 on the threads. These screws are best inserted from 

inside

 the foil, 

not from the outside.  
 
Forestay top terminals vary from boat to boat. If the Foil End Cap (21) will not fit over the 
forestay top terminal, feed the Foil End Cap onto the forestay from the bottom of the 
forestay at this stage.   
 
Feed the pvc sleeving onto the wire from the end and then feed the forestay into the foil 
before fitting the lower terminal. If this operation is difficult, reduce friction by applying 
washing up liquid to wre before inserting into the sleeve. 
 

The Swivel & Foil End Cap

 

 
Slide the swivel (4) onto the foil making sure the outer casting of the swivel is at the top 
and the inner casting  is at the bottom.   
The Foil End Cap (21) consists of 3 parts: an outer plastic end cap and two inner half 
bearings (22). Before fitting the end cap, check that the hole in the plastic inner half 
bearings is the correct size for the forestay. Drill out if necessary to forestay di 
1mm. 
Fit end cap to foil as follows: slide plastic end cap over forestay eye terminal* and over 
the two profiled plastic half bearings while holding the latter together around the forestay. 
Fit bearings into top of foil and rivet the cap to the foil using the two alloy rivets supplied. 
 

Содержание Z400

Страница 1: ...S05 doc Z400F Z500F Z600F Dimensions Form FS 1 456 Z700F Z800F Dimensions Form FS 1 780 Z1000F Z1200F Dimensions Form FS 1 1012 Halyard Diverter Method 1 FS 3 gendiv01 skd Halyard Diverter Method 2 FS...

Страница 2: ...inium Luff Foil 7 Drum Screws 8 Tack Eye 9 Guard 10 Drum 11 Guard Attachment 12 Locking Joint 13 Locking Screw 14 Bushing for Lower Drum Bolt 15 Lower Drum Bolt Z400F Z600F M10 x 60 Z700F Z800F M12 x...

Страница 3: ...GENINS05 Page 3 28 08 2014 COMPONENT DRAWINGS...

Страница 4: ...GENINS05 Page 4 28 08 2014...

Страница 5: ...set screws m6x8 16 Use Loctite 638 on the threads These screws are best inserted from inside the foil not from the outside Forestay top terminals vary from boat to boat If the Foil End Cap 21 will no...

Страница 6: ...st and the drum is inside the guard rails Fit a diverter see below Halyard diverter Please note that it is essential to fit a diverter to the foresail halyard above the top swivel of the furling syste...

Страница 7: ...alternative onto the pulpit and tension up 4 Disconnect the foil from the drum assembly while holding the foil remove the two socket headed Drum Screws 7 from the upper drum tube then allow the foil t...

Страница 8: ...released Action release the sheet e The halyard is too tight Action Ease off the halyard f Furling line fouled on the drum Action Unfurl remove the sail Rewind the furling line Unfurl with slight tens...

Отзывы: