background image

BoSS StairMAX 

User Guide

5

StairMax 600 

Assembly Procedure

3

Link these two frames with two horizontal and two 
diagonal braces as shown in the illustration, to 

form the tower base - start by clipping the horizontal 
braces to the frame uprights.

4

Fit the platform to the top rungs of  the two end 
frames. Make sure all four platform end hooks are 

in contact with the top rungs, then secure in place by 
engaging the hook latches (see illustration). Fit a 
standard frame to the top end of  the frame that is at 
the lower step, secureing it in place with the interlock 
clips. Fit the gate frame to the top of  the frame that is 
resting on the uper step. Make sure that the access 
bar is positioned so that it opens in towers the tower. 

Содержание StairMAX 600

Страница 1: ...StairMAX Aluminium Tower 600 700 850 Climbing Rung 3T Through The Trapdoor Method User Guide Edition July 2008 TM...

Страница 2: ...on this tower whilst those likely to excert moderate sideways force should be carried out with due care Never use boxes steps etc to gain extra height Never reach too far out to one side If the tower...

Страница 3: ...Inspect tower prior to use Tower upright and level Castors locked and legs correctly adjusted Diagonal braces fitted Stabilisers outriggers fitted as specified Platforms located and windlocks on Toeb...

Страница 4: ...ce x6 Diagonal Brace x2 Stabiliser x1 Adjustable Leg x4 Base Plate x4 End Toeboard x2 Side Toeboard x2 Tower Dimensions Maximum safe working height 3 7m Maximum overall height 3 5m Maximum platform he...

Страница 5: ...ually they are equaly extended so that they stand level These will now be reffered to as base frames 2 Fit an aditional frame to one of the base frames and engage the interlock clips Place the base fr...

Страница 6: ...m to the top rungs of the two end frames Make sure all four platform end hooks are in contact with the top rungs then secure in place by engaging the hook latches see illustration Fit a standard frame...

Страница 7: ...applications in addition to any method of stabilisation used Please contact your supplier ro hire shop for details If stabiliser s are required they must be fitted to the corner s of the end frame on...

Страница 8: ...the bottom rung of each base frame i e 75kg at each end Please contact your supplier or hire shop for details B The tower is positioned up against a wall on one side and a stabiliser is fitted on the...

Страница 9: ...tructions to ensure your system is erected easily and safely using the 3T Through The Trapdoor method The law requires that personnel errecting dismanatling or altering towers must be competent Any pe...

Страница 10: ...load is 275kg 606lb per platform level Towers must always be climbing from the inside using the built in ladder during assembly and use It is recomended that towers should be tied to a solid structure...

Страница 11: ...und clearnce for stabilisers outriggers contact your supplier for advice Ballast must be of solid materials ie not water or loose sand and should not be positioned to overload individual legs Ballast...

Страница 12: ...ches in motion telegraph wires whistle 6 25 31 11 14 Gale Force Walking is difficult 8 39 46 17 21 Beware of open ended buildings which can cause funneling effect Do not abuse equipment Damaged or inc...

Страница 13: ...tying in a tower please contact your supplier or Youngman Maintenance Storage Transport All components and their parts should be regularly inspected to identify damage particularly to joints Lost or b...

Страница 14: ...nd Frame 2 2 4 Rung Guardrail Frame 1 0m high x 0 85m wide 1 1 7 Rung Span Frame 1 75m high x 0 85 wide 2 3 Trap Door Deck 2 2 Horizontal Brace 5 9 Diagonal Brace 5 6 Side Toeboard 2 2 End Toeboard 2...

Страница 15: ...4 Rung Guardrail frame 1 0m high x 0 85m wide 1 1 7 Rung Span Frame 2 0m high x 0 85 wide 1 2 Trap Door Deck 2 2 Horizontal Brace 5 9 Diagonal Brace 6 8 Side Toeboard 2 2 End Toeboard 2 2 Toeboard Hol...

Страница 16: ...at base plates are used instead of castors 1 Push 4 base plates onto adjustable legs Insert adjustable leg assemblies into Walk through base frame as shown Repeat for second Walk through base frame 2...

Страница 17: ...he climbing side above the 5th rung of the portal frame with the claw facing outwards The frame will now be self supporting Note All locking claws must be open before fitting 4 Position the second por...

Страница 18: ...the higher end frame and the 10th rung of the lower end frame Ensure the frames are vertical and level by checking with a spirit level and setting the adjustable legs accordingly 6 Fit a diagonal bra...

Страница 19: ...he end frame Where possible the Stabilisers must also have a minimum outstand of 1 2m 8 Fit a temporary trapdoor deck on the 7th rung of the upper frame as shown Climb up the inside of the tower and f...

Страница 20: ...rapdoor deck on the 11th rung counting at the higher end 10 Stand on the temporary deck and by using the trapdoor of the higher deck as a guardrail fit the 4 rung frame to the lower end of the tower F...

Страница 21: ...next height the 4 rung frame at the lower end should be replaced with a lift frame 1 75m for 700 2 0m for 850 The 4 rung frame should then be positioned at the higher end of te tower Diagonal braces...

Страница 22: ...e edge of the deck on all sides 850 StairMax Lock yellow plastic toeboard clips over rung and deck claw as shown Position as A on right hand deck claw On other side of the working plaform position the...

Страница 23: ...youngmangroup com 22 Stabilisers StairMax 600 StairMAX 700 850 1 5m Min 1 2m Min 1 2m Min Min Min...

Страница 24: ...on about this product or any other products and services please contact Youngman Group Ltd The Causeway Maldon Essex CM9 4LJ United Kingdom t 44 0 1621 745900 f 44 0 1621 859845 e sales youngmangroup...