                                                    Product Conveyance Installation 

 

2.

 

Transportation & Installation 

2.1

 

Transportation 

Units are normally shipped ex-works. They are inspected, tested, and packaged prior to dispatch, carefully loaded 
into containers, shipped to country of destination, unloaded, and delivered to jobsite. 

Immediately  upon  receipt  at  jobsite,  inspection  should  be  made  for  any  damage,  which  must  be  reported  to 
Johnson Controls within 24 hours of receipt of goods. 

When  moving  the  fan  coil  unit,  please  handle  with  care  and  prevent  the  coil  water  inlet,  outlet  and  drain  pipes 
from  getting  bent  or  damaged.  Use  only  approved  lifting  equipment.  Do  not  carry  the  unit  by  the  fan  or  motor 
assembly to avoid distortion.

 

  

Package for YECFC01~03 Units                                        Package for YECFC04&05 Units 

2.2

 

Acceptance 

All  items  must  be  checked  against  customer  purchase  order,  delivery  docket,  and  submittal  drawings  for 
correctness  and any  claims  for  non-compliance  or  short  supply  reported  to  Johnson Controls  within  72  hours  of 
delivery. 

2.3

 

Storage 

If the unit is stored on the jobsite, it should be protected against exposure to the elements. 

Specifically  units  should  be  securely  protected  from  theft,  accidental  damage,  water  ingress,  moisture  damage, 
rusting, or dust. 

2.4

 

Lifting of the Unit 

During the installation process, be careful to prevent the unit from any damage due to improper lifting and rigging. 
Use  only  approved  lifting  equipment.  Safety  should  always be  a priority.  Only  authorized  lifting  equipment  and 
trained installers should be used. Equipment should be installed in accordance with all national safety codes.

 

 

2.5

 

Points for Attention before Installation 

Before the unit is installed, the following should be verified during the construction of the building: 

1. Water Supply 

2. Power Supply 

3. Supply air, return air, and outside air ducting (if applicable) 

4. Ceiling Mounting points 

5. Service Access 

Содержание YECFC

Страница 1: ...YECFC Fan Coil Unit Installation Operation Maintenance Manual FORM NO 6A4Y A01A NE EN Air Flow 150 750L S...

Страница 2: ...7 2 4 Lifting of the Unit 7 2 5 Points for Attention before Installation 7 2 6 Points for Attention during Installation 8 2 7 Installation 8 3 Startup Running of Product 9 3 1 Check before Start Up 9...

Страница 3: ...Corporation can supply many types and models of fan coil unit Users can select applicable products according to their own taste the installation space and position etc Detailed types and models are e...

Страница 4: ...Overview of product 2 01 02 A CR Model Cooling and Heating 03 3 4R Model Cooling...

Страница 5: ...Overview of product 3 03 A CR Model Cooling and Heating 04 05 3R Model Cooling...

Страница 6: ...Overview of product 4 04 05 4R Model Cooling 04 05 AR Model Cooling and Heating...

Страница 7: ...5 317 558 317 214 1870 x 214 1845 x 274 Notes 1 Facing the air outlet the left type unit has pipes on the left side right type unit opposite 2 Filter frame is provided as standard Filter media is prov...

Страница 8: ...noise is of concern The installing contractor is responsible to commission fan coil units with minimum and maximum control voltage settings commensurate with the units design operating range The fan...

Страница 9: ...docket and submittal drawings for correctness and any claims for non compliance or short supply reported to Johnson Controls within 72 hours of delivery 2 3 Storage If the unit is stored on the jobsit...

Страница 10: ...duled in the table in this manual Do not overtighten the water connections Torque should not exceed 50 N M so as to avoid breakage Significant care should be taken when attaching water pipes or water...

Страница 11: ...utomation system such as Johnson Controls Metasys or from an advanced thermostat with a 0 10v variable speed fan output such as Johnson Controls TEC3000 range Minimum control voltage would typically b...

Страница 12: ...perature controller are not prohibited Wire Size recommended is based on 40 ambient temperature Only copper wire can be used Please follow the local electrical codes and wiring standards in all cases...

Страница 13: ...ir Filter Air filters should be checked and cleaned or replaced as necessary on a periodic basis Typically inspect air filters every 3 months noting that filter cleaning and replacement frequency is d...

Страница 14: ...ses coil velocity and increased unit noise level Increased air flow rate leads to risk of moisture carryover where coil face velocity exceeds 2 5 m s Decrease fan speed as required 5 3 High Noise and...

Страница 15: ...trols com FORM NO 6A4Y A01A NE EN SUPERSEDES 6A4Y A01A ND EN Johnson Controls is committed to the continuous product improvement Please note the product design may change without notification This man...

Страница 16: ...14...

Отзывы: