Section 3 – Handling and storage
Delivery and Storage
To ensure consistent quality and maximum reliability,
all units are tested and inspected before leaving the fac-
tory. Units are shipped completely assembled and con-
taining refrigerant under pressure. Units are shipped
without export crating unless crating has been speci-
fied on the Sales Order.
If the unit is to be put into storage, before installation,
the following precautions are observed:
• The unit must be “blocked” so that the base is not
permitted to sag or bow.
• Ensure that all openings, such as water connec-
tions, are securely capped.
• Do not store where exposed to ambient air tem-
peratures exceeding 110°F (43°C).
• The condensers should be covered to protect the
fins from potential damage and corrosion, particu
-
larly where building work is in progress.
• The unit should be stored in a location where there
is minimal activity in order to limit the risk of ac-
cidental physical damage.
• To prevent inadvertent operation of the pressure
relief devices the unit must not be steam cleaned.
• It is recommended that the unit is periodically in-
spected during storage.
Inspection
Immediately upon receiving the unit, it should be in-
spected for possible damage which may have occurred
during transit. If damage is evident, it should be noted
in the carrier’s freight bill. A written request for inspec-
tion by the carrier’s agent should be made at once. See
Instruction manual,
Form 50.15-NM
for more informa-
tion and details.
Major damage must be reported immediately to your
local Johnson Controls representative.
Unit Rigging
Use spreader bars to avoid lifting chains hitting the
unit.
Never lift the unit using a forklift or by
hooking to the top rails. Use only the lift-
ing holes provided.
Lifting Instructions are placed on a label on the unit
and on the shipping bag.
The unit should be lifted by inserting
hooks through the holes provided in unit
base rails. Spreader bars should be used
to avoid crushing the unit frame rails with
the lifting chains (See Figure 7).
Figure 7 -
Unit Rigging
LD14326
Содержание YCUL0020
Страница 4: ...JOHNSON CONTROLS 4 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 10: ...JOHNSON CONTROLS 10 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 14: ...JOHNSON CONTROLS 14 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 40: ...JOHNSON CONTROLS 40 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 53: ...JOHNSON CONTROLS 53 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 55: ...JOHNSON CONTROLS 55 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 57: ...JOHNSON CONTROLS 57 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 59: ...JOHNSON CONTROLS 59 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 61: ...JOHNSON CONTROLS 61 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 63: ...JOHNSON CONTROLS 63 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 65: ...JOHNSON CONTROLS 65 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 67: ...JOHNSON CONTROLS 67 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 69: ...JOHNSON CONTROLS 69 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 71: ...JOHNSON CONTROLS 71 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 73: ...JOHNSON CONTROLS 73 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 75: ...JOHNSON CONTROLS 75 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 77: ...JOHNSON CONTROLS 77 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 79: ...JOHNSON CONTROLS 79 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 81: ...JOHNSON CONTROLS 81 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 83: ...JOHNSON CONTROLS 83 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 85: ...JOHNSON CONTROLS 85 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 87: ...JOHNSON CONTROLS 87 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Страница 102: ...JOHNSON CONTROLS 102 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 108: ...JOHNSON CONTROLS 108 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 158: ...JOHNSON CONTROLS 158 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Страница 177: ...JOHNSON CONTROLS 177 Form 150 63 NM9 Issue date 5 20 2021 Notes...