 CAUTION

Turn off power supply to TB820D before wiring. Power rating must comply with TB820D 

specifications. Power voltage must match with the one indicated on the name plate.

 WARNING

●  You must install external power supply switch or circuit breaker for power supply.

●  The external power supply switch or a circuit breaker must comply with a current 

rating of 5Aor IEC60947-1 or IEC60947-3

●  Yokogawa recommend installing the external power supply switch, circuit breaker 

and TB820D all in the same location.

●  Install the external power supply switch or circuit breaker to the place where 

operators access easily. To alert users, put a label on the external power switch.

●  Fix securely onto constructions or walls all power lines including wire cables of 

power supply  by using stanchion, cable rack, conduit or vinyl band.  

Unplugged cables are dangerous and may cause an electric shock.

CAUTION

When you open the front cover on the detector and Relay Box, make sure the screws 

are completely out of the screw holes, and then open the front coverl slowly in order not 

to damage the threaded parts on the housing. If the threaded parts are damaged and 

the screws cannot be tightened, the waterproof performance will deteriorate.

  Wiring of TB820D

WARNING

Never let the power cable touch SENCOM cable, resulting in failure to comply with 

safety requirements.

WARNING

● 

Use wiring cables with heat resistance above 75 °C, waterproof rating IP65 or 

higher.

● 

Tightening torque to the four screws of Smart Box cover is 1.4 N·m.

●  For power supply, wire cables with a flammability rating of UL 2556 VW-1 or 

equivalent.

Содержание TB820D

Страница 1: ...User s Manual TB820D Right Angle Scattered Light Turbidity Detector Start up and Safety Precautions IM 12E01B30 01EN IM 12E01B30 01EN 1st Edition...

Страница 2: ...the product printed manual FLXA402T Liquid Analyzer for Turbidity and Chlorine Installation and Wiring IM 12A01G01 02EN Online manual FLXA402T Liquid Analyzer for Turbidity and Chlorine Operation of...

Страница 3: ...and service Yokogawa products and parts are guaranteed free from defects in workmanship and material under normal use and service for a period of typically 12 months from the date of shipment from th...

Страница 4: ...ging Repair work should be done at grounded workstations using grounded soldering irons and wrist straps to avoid electrostatic discharge CAUTION The Instrument is packed carefully with shock absorbin...

Страница 5: ...safety symbols are used on the product as well as in this manual WARNING This symbol indicates that an operator must follow the instructions laid out in this manual in order to avoid the risks for the...

Страница 6: ...6 IM 12E01B30 01EN 1st Edition Mar 30 2021 00 u Compliant Standards EMC RCM EN 55011 Class A Group 1 Korea Electromagnetic Conformity Standard Class A...

Страница 7: ...ose for RCM General purpose for KC General purpose Relay box for solenoid valve NN A5 Without relay box for solenoid valve Relay box for solenoid valve Ultrasonic cleaning NN U1 Without ultrasonic cle...

Страница 8: ...d at or as near to room temperature as possible allows for sufficient maintenance space with easy maintenance access allows for drainage For information on FLXA402T read the user s manual Install the...

Страница 9: ...1 L 202 N 002 G U1 U2 U3 S L N G 32 NC 31 C 33 NO S1 42 NC 41 C 43 NO S2 72 NC 71 C 73 NO S4 61 62 mA1 65 66 mA2 81 82 mA3 85 86 mA4 21 22 24 SHLD 63 87 88 SHLD 89 A 91 B 92 GND 93 SHLD 94 Termination...

Страница 10: ...er switch Fix securely onto constructions or walls all power lines including wire cables of power supply by using stanchion cable rack conduit or vinyl band Unplugged cables are dangerous and may caus...

Страница 11: ...nused cable inlets with the supplied cable glands and close up plugs Refer to IM 12E01B30 02EN for details WARNING The minimum cross sectional area of the protective grounding wire should be 0 75 mm2...

Страница 12: ...n the smart box Connect the cable complying with the figure below Ground Terminal 101 102 201 202 301 302 Power Terminal To Converter terminal To Detector terminal n Wiring of PG400 For wiring PG400 c...

Страница 13: ...ng are all correctly provided 2 Set up the desiccant 3 Run water and check that there is no water leakage 4 Turn on the power and set to Maintenance mode 5 Configure parameters on the converter and de...

Страница 14: ...intain the housing s weatherproof integrity against water and water vapor The pH measurement uses high impedance sensors glass electrode Keep the moisture out of the converter inside CAUTION Never use...

Страница 15: ...ety Precautions 15 IM 12E01B30 01EN 1st Edition Mar 30 2021 00 Revision record Mar 2021 1st Edition Newly released Yokogawa Electric Corporation 2 9 32 Nakacho Musashino shi Tokyo 180 8750 JAPAN http...

Отзывы: