background image

Y I N G L I S O L A R .CO M

©

 Yingli Energy Development Company Limited           

GB Modules Installation and User Manual  Page 8 

I N S T A L L A T I O N   M E T H O D

1. Mounting hole installation (fixed bracket)

Type

Mechanical load (Pa)

Safety factor

Schematic diagram

Purlin perpendicular to 

long-side frame

+3600

- 1600

1.5

Purlin parallel to 

long-side frame

+1600

 - 1600

1.5

Notes:

  To maximize mounting longevity, Yingli Solar strongly recommends the use of corrosion proof (stainless steel) attachment hardware.

  To check whether the surface of the beam is flat and smooth, or add rubber pads on the beam to prevent the module from being crushed when it is pressed down.

  Parts in contact with the modules should use flat stainless steel washers of minimum 1.4 mm thickness with an minimum outer diameter of 15.57 mm.

  Modules can be attached using the mounting holes (2 holes of φ9×14 mm of one long-side frame, ≥ 1300 mm spacing) on the back of the module frame, by fix-

ing the module to the support rails with bolts.

  Secure the module in each mounting location with M8 bolts and matching flat washers, spring washers and nuts, and tighten to a torque of 14~20 N·m. The 

tightening steps as follows: use torque wrench to tighten nut to target torque, nut loosen 90~180 degrees, finally tighten the nut to the target torque and reduce the 
torque attenuation.

2. Mounting hole installation (1P tracker)

Type

Mechanical load (Pa)

Safety factor

Schematic diagram

Purlin parallel to 

long-side frame

+1600

 - 1600

1.5

Notes:

  To maximize mounting longevity, Yingli Solar strongly recommends the use of corrosion proof (stainless steel) attachment hardware.

  Parts in contact with the modules should use flat stainless steel washers of minimum 1.4 mm thickness with an minimum outer diameter of 15.57 mm.

  Modules can be attached using the mounting holes (2 holes of φ7×10 mm of one long-side frame, 400 mm spacing for special tracker, or 2 holes of φ9×14 mm 

of one long-side frame, spacing ≥ L/3, L represents the length of the long side of the module) on the back of the module frame, by fixing the module to the support 
rails with bolts.

  Secure the module in each mounting location with 2 M6 bolts or 2 M8 bolts, and matching flat washers, spring washers and nuts, and tighten to a torque of 14~20 

N·m. The tightening steps as follows: use torque wrench to tighten nut to target torque, nut loosen 90~180 degrees, finally tighten the nut to the target torque and 
reduce the torque attenuation.

Содержание YLM 144CELL 182PERC

Страница 1: ...ication requirements has been verified by an independent certification laboratory This Installation and User Manual is available in different languages In cases of discrepancy between versions the Eng...

Страница 2: ...ng so may degrade performance or cause irreparable damage and will void any applicable warranties If it is necessary to store PV modules prior to installation the PV modules should remain inside the p...

Страница 3: ...suitable cross sectional areas that are approved for use at the maximum short circuit current of the PV module Yingli Solar recommends installers use only sunlight resistant cables qualified for dire...

Страница 4: ...ult in galvanic corrosion An addendum to UL Standard 1703 Flat Plate Photovoltaic Modules and Panels recommends metal combinations not exceed an electrochemical potential difference of 0 5 Volts The f...

Страница 5: ...hment Figure 12 Installation rails The large size modules are mounted with four outer holes with max mechanical loads of 5400 Pa snow front and 2400 Pa wind back Top down Clamps Third party clamps tha...

Страница 6: ...e materials that could scratch or damage the glass surface Failure to comply with these requirements may adversely affect the PV module performance Yingli Solar PV modules are designed to withstand hi...

Страница 7: ...l characteristics are within 10 percent of the indicated values of Isc Voc and Pmax under Standard Test Conditions irradiance of 1000 W m2 AM 1 5 spectrum and a cell temperature of 25 Refer to module...

Страница 8: ...f 14 20 N m The tightening steps as follows use torque wrench to tighten nut to target torque nut loosen 90 180 degrees finally tighten the nut to the target torque and reduce the torque attenuation 2...

Страница 9: ...ashers of minimum 1 4 mm thickness with an minimum outer diameter of 15 57 mm Modules can be attached using the mounting holes the number of mounting holes used for a single long side frame 2 includin...

Страница 10: ...when it is pressed down L represents the length of the long side of the module the described distances are from the module edge to the middle of the clamp The long side frames of the module are fixed...

Страница 11: ...ropes are required to secure the modules to the forklift with a tensile strength greater than 2000 kgf 2 Pass the forearm of the anti tilting bracket through the pallet insert the two bolts into the...

Отзывы: