The deployment procedure varies according to:
Radio transmission and reception through the floors
Similarities and differences between floors
The study of transmission and reception through the floors determines whether several
floors will be included in a same coverage area. There are two approaches in
deploying a multiple storey building:
If the degree of attenuation of the building construction materials (e.g., wood) of
the building is low, deploy the base stations as follows:
1.
Place the base station on an intermediate floor on the site.
2.
Without moving the base station, go to the floor above, then measure the
horizontal coverage at this location.
3.
Without moving the base station, go to the floor directly below and measure
the horizontal coverage at this location.
4.
Arrange the base stations with one base station in the centre and the others
surrounding it, as shown in the following diagram.
If the degree of attenuation of the building construction materials (e.g., metal) of
the building is high, follow the above introduced steps (single floor) to deploy each
floor as individual parts. For more information, refer to
Deployment in a Single Floor
Building
on page
6
.
Note
The similarities between the floors do not exclude variations in the radio transmission
and reception. You are advised to check the sound quality on each floor.
We recommend that you do not deploy base stations on the same vertical line.