![background image](http://html.mh-extra.com/html/yamato/adl311/adl311_instruction-manual_905262014.webp)
12
4. Operating procedures
Preparations
(4) Connect the nipple (
φ
7) at the rear of the upper frame and the compressor or other pressurized
air units with the included pressure-proof hose and then securely tighten it using a hose band.
Adjust the discharge pressure of the compressor to be constant (0.3MPa or less) using the
pressure reducing valve.
(5) Cooling the spray nozzle
The cooling mechanism for the spray nozzle is pre-installed (nozzle O.D.:
φ
10.5). When you
operate the unit under operating conditions under which the spray nozzle is likely to clog,
connect a separate cooling water circulating unit (such as CF300) or to a tap water faucet to
allow cooking water circulating.
(6) Open the package of the mini spray attachment (GF300) and check for damages to glass and
other parts or any missing parts.
(7) Install the distributor and aluminum honeycomb assembly onto the top of the unit.
Install the O-ring P16 into the
φ
20 groove on the top of the distributor.
(install using three M6 x 20 hex bolts, spring washers, flat washers each)
O-ring P145
O-ring P135
Install into the groove
on the bottom surface
Hex bolts at three
positions
Aluminum honeycomb (installed from the
top of the distributor)
Compressor connecting nipple
Not used
Optional for GAS410
Nozzle IN
Nozzle OUT
Temperature sensor
connecting socket
O-ring P16
Install into the
φ
20
groove on the top of
the distributor
Содержание ADL311
Страница 36: ...34 11 Wiring Diagram ADL311 Wiring Diagram ...
Страница 38: ...36 11 Wiring Diagram ADL311S Wiring Diagram ...