Installation Guide
On-site installation procedure PV monitoring with Xemex KWHIQ meter
Installation
Choose a suitable location with sufficient signal strength
The meter should be installed in a dry and well-ventilated location. The meter or the installation board
should be placed against a robust, fire-resistant solid wall. In case of any doubt (e.g. in basements),
use a
telephone and reference meter
to check the signal strength of the mobile network in advance.
Fix the meter
Respect the safety regulations and act in accordance with the user manual of the meter.
Dimensions:
210mm x 131,6mm x 85.8mm
Materials:
– Pozidriv screwdriver PZ no.2 for the screws on the terminal block.
– 3 Self-tapping M5 screws with countersunk head for fixing to the wall or panel.
– Drill with M5 stone drill bit and 3 plastic plugs for installation against a concrete wall.
Check the meter before connecting it. Only connect the meter if there is no visible
or audible damage or defect (loose parts). Meters that have been dropped
may not be installed, even if no damage is visible. They must be returned to
the manufacturer for inspection. Internal damage may cause short circuits or
malfunction.
The meter is fixed at 3 points: 1 hook at the top and 2 screw holes.
The hook can be adjusted to 3 positions. First hang the meter on the hook at the top
and then attach the 2 screws.
Connect the meter
First de-energise the side of the circuit to which the meter is to be connected. Make sure that the
circuit cannot be re-energised by accident.
Connect the meter as indicated below.