©2001 Xantrex Technology Inc.
15
Operation and Test
NOTE: Refer to the inverters operators manual for setting the RY7
relay for either RUN or GLOWSTOP (whichever is appropriate for
the generator).
NOTE: Ensure the inverters MAXIMUM AC AMPS IN switch is in
the AC2 position otherwise generator auto-start will not operate
properly.
Immediately after installation, the GSM should be tested for proper
operation of the generator and error indicator.
Ensure the GENERATOR RELAY switch on the GSM is in the ON
(ENABLED) position and the INVERTER ERROR relay is in the RELAY
READY position.
Reconnect all power to the inverter and generator start circuits. Turn ON
the inverter. The blue INVERTER OPERATIONAL LED should immediately
turn ON.
Using the SWRC remote, press the green GEN MENU button to access the
generator menu. Select ON from the display. The generator should begin
to operate and the appropriate relay LEDs should be illuminated on
the GSM.
NOTE: The LEDs will turn ON differently, depending upon the
function selected in the SWRCs RY7 menu. On two-wire configura-
tions, the RY8 relay is not used.
If the test passes, select OFF from the SWRCs GEN MENU display.
When the generator stops, select AUTO from the GEN MENU display (if
desired) for automatic generator operation.
If an external alarm is connected to the GSM, turn the INVERTER ERROR
switch to the RELAY TEST position. The external device should activate.
Place the INVERTER ERROR switch in the RELAY READY position.
NOTE: If the tests did not pass (i.e., the generator did not start or
stop), recheck the wiring to the generator auto-start circuits and
GSM for proper relay contact selection (N.O. or N.C.). Also check
the settings for the RY7 relay (using the SWRC) and ensure they are
correct.