5
Gigant
Caution
Delivery / Transportation
Delivery to site
Transportation
Required space
Air-conditioning units KG/KGW Gigant are supplied in transportable units.
Upon arrival on site, the unit or its components must be checked for any
transportation damage.
In case of damage or suspected damage, this must be specified on the shipping
note by the recipient and countersigned by the forwarder.
The recipient must relay the respective details directly to WOLF.
Units may only be transported in their fitting position.
Exception: KGXD 250 is laid flat (90° turn) for transportation.
Transport units with carrying straps!
When using fork lift trucks or rollers, ensure that the lifting fork or rollers are
positioned underneath the frame profiles and not underneath the bottom panels.
When using lifting eye bolts (on request), the length of the lifting cable must
correspond to at least the distance L between the eye bolts. Ensure identical
cable lengths!
Units with more than 4 eye bolts must be lifted with the aid of a lifting beam!
For assembly, operation and maintenance, at least a space equivalent to the
width of the unit should be available on the operating side (see table below).
Space required for assembly, operation and maintenance:
Fan section
0.8 x unit width
Cooling coil/heating coil and
surrounding coil
1 x unit width + 250 mm
Filter section
up to KG 100
1 x unit width
from KG 160
0.5 x unit width
For double units installed side-by-side, the above space for assembly, operation
and maintenance is required on both sides.
Units requiring a drain trap (washer, humidifier, cooling coils, KGX/KGXD, drop
eliminator) must be installed in such a way, that the proper installation and
function of the drain trap is guaranteed (pay attention to foundation height).