7.2     Installation of the complete pump set

 

 

Before  any  installation  work  is  carried  out,  the  pumpset 
should  be  inspected  for  damage  that  may  have  occurred 
during handling, transport & storage. 

 

Installation within a building: install the pump in a dry, well 
ventilated and frost-resistant room. 

 

Pumping  machinery  should  have  adequate  access  and 
working  room  for  maintenance  operations.  Adequate 
overhead  space  for  lifting  devices  and  working  clearance 
must be provided. 

 

Installation outside a building (outdoor installation): 

 

Install the pump with a suitable protection to avoid rainfalls 
strong wind and particles which can damage the pumpset. 

 

Avoid exposure of the pumpset to direct sunlight. 

 

An  appropriate  solution  to  avoid  frost  must  be 
implemented. 
 

 CAUTION!  Risk  of material damage!

 

Ensure  sufficient  ventilation/heating  if  the  ambient 
temperature exceeds/falls below the permitted limit values. 

 

Carry  out  all  welding  and  soldering  work  prior  to  the 
installation of the pump. 
 

CAUTION! Risk  of material damage!

 

Dirt  from  the  pipe  system  can  destroy  the  pump  during 
operation. Flush the pipe system prior to the installation of the 
pump. 

 

Provide shut-off valves in front of and behind the pump. 

 

7.2.1   Foundations (figures 2&3 Pg. 1&2)

 

The foundation should be sufficiently substantial to absorb 
any vibration and to form a permanent, rigid support for the 
base plate. The foundation must get large dimensions. 
Generally, the weight of the foundation is around 
2  to  3  time  the  pump  set  weight.  This  is  important  in 
maintaining  the  alignment  of  a  direct  connected  unit.  In 
building the foundation, the top surface level should be low 
by 1inch to accommodate packer plate thickness/height and 
surface  should  be  rough  for  bonding  of  fresh  grouting 
material.    Foundation  bolts  of  the  proper  size  should  be 
embedded in the concrete, located by template (refer figure 
3 Pg. 1). 

 

 
 

 
 
 
 
 
 
 
 
 

Foundation  bolt 

 

1     Erection packers 
2     Finish grout 
3     Concrete 

             

NOTE: 

Leave top of foundation  rough! Do not finish with trowel. 

 

A  pipe  sleeve  about  2  ½  diameters  large  than  the  bolt 
should be used to allow movement for the final positioning 
of the bolts. For installations where a low level of noise is 
expected,  built  the  foundation  in  a  pit  lined  with 
appropriate insulation material in order to avoid vibration 
transmission to the ground. 

 

              CAUTION! Risk of material damage!

 

Do  not  hold  the  pump  by  the  motor/module  when 
tightening the screwed connections. Apply the wrench 
surfaces to the suction/pressure port inserted. 

 

It  is  insufficient  to  check  level  on  the  machined  pads  of 
base  plate  with  a  spirit  level  because  it  is  possible  that 
some  types  of  errors  will  not  be  revealed  or  will  be 
accepted  as  being  within  acceptable  limits.  These 
distortions  as  showed  in  figure  4  Pg.2.  Therefore,  it  is 
necessary to use  

 

I-beam straight edge along with engineer

’s

 master level. 

 

            7.2.2   Levelling and installing the base plate 
 

 

             CAUTION! Risk of material damage!

 

Pumps and drivers that are received  with both  machines 
mounted  on  a  common  base  plate  are  checked  for 
alignment before  shipment. However, during shipment, 
storage  it may get  disturbed. 

 

 

Use  I-beam  type  straight  edge  and  an 

engineer’s  master 

level (with accuracy of 0.05 mm / 250 meter) for levelling 
the  base  plate.  I-beam  should  rest  on  the  machined 
surfaces  of  the  base  plate,  or  on  the  levelling  pads  if 
provided.  These  machined  surfaces  where  level  is  being 
checked must be clean and free from paint, burrs etc. 

 

Check datum position of base frame as given in G.A.  Adjust 
the level of the base plate by inserting shims between the 
base  plate  and  the  packer  plate  until  the  bed  plate  is 
levelled  and  supported  on  all  the  packing  plates  at  the 
height  required  for  the  connection  of  suction  and 
discharge  branches.  For  checking  the  levels  across  two 
pads,  use  I-

beam  type  straight  edge  and  an  engineer’s 

master level. Level should be achieved within 0.05 mm per 
250  mm.  There  should  two  packer  plates  at  each 
foundation  bolt  and  additional  packer  to  be  provided 
intermittently if distance between two foundation bolts is 
more than 500 mm. Packer plates should be machined and 
of adequate size with minimum 25 mm thick. 

 

When the base plate is levelled, grout the foundation bolts 
only.  Care  should  be  taken  so  as  not  to  disturb  the 
verticality of foundation bolts. For grouting use rich mix of 
1:  1:2  of  cement,  sand  and  gravel  below  12  mm. 
Alternatively quick setting grout mix can be used. 

 

When  the  grout  has  set,  gently  but  firmly  tighten  the 
foundation  bolts.  Care  must  be  taken  not  to  distort  the 
base plate or loosen the foundation bolts in the grout by 
excessive tightening. 

 
 

 

 
 
 
 
 
 
 
 
Installation and operating  instructions WILO-Split Case Pumps                                                                                                                                                                         

16

 

Содержание WILO-SCP

Страница 1: ...WMPPPL_IOM_SCP_RV 004_20201226 WILO SCP en Installation and operating instructions ...

Страница 2: ...that install and maintain the pump shall be responsible for hassle free installation operation or maintenance of the product This document is prepared with at most care to ensure correct and accurate information enabling the user to have trouble free installation and operational support However there can be few areas for improvement to make this document error free We welcome your valuable suggest...

Страница 3: ...lete pump set Page No 9 Point no 3 3 1 Fig 2 Lifting of complete pump Page No 9 Point no 3 3 1 Fig 3 Fig 3 Foundation pump set Page No 17 Point no 7 2 1 Fig 4 Installation and operating instructions WILO Split Case Pumps 1 ...

Страница 4: ...oint no 7 2 1 Fig 5 Angular Radial Alignment Page No 18 Fig 6 Maximum Allowable Forces Moments for Cast Iron Flanges Page No 19 Fzs Fzd Mzs Mzd Fyd Myd Mxd Fxd Fys Mys Fxs Mxs Installation and operating instructions WILO Split Case Pumps 2 ...

Страница 5: ...Fig 7 Suction Line Page No 20 Point no 7 2 5 Fig 8 1 Suction Line Page No 20 Point no 7 2 5 Fig 8 2 Suction Line Page No 20 Point no 7 2 5 Installation and operating instructions WILO Split Case Pumps 3 ...

Страница 6: ...g 8 1 Good and Bad Suction Line Layouts Page No 20 Point no 7 2 5 Fig 8 2 Good and Bad Suction Line Layouts Page No 20 Point no 7 2 5 Ø 4xØ Installation and operating instructions WILO Split Case Pumps 4 ...

Страница 7: ...nt no 7 2 5 Fig 9 Stuffing Box Packing Page No 20 Point no 7 2 7 Fig 10 Lifting of the pump with engine Page No 9 Point no 3 3 1 10 Fig 8 3 Good and Bad Suction Line Layouts Page No 20 Point no Installation and operating instructions WILO Split Case Pumps 5 ...

Страница 8: ...htening Seen NOTE The above example shown is for pump with 26 bolts This sequence of tightening the diagonally opposite bolts is to be followed for other pumps with different number of bolts Installation and operating instructions WILO Split Case Pumps 6 ...

Страница 9: ... Accessories 12 6 Description andfunction 12 6 1 Description of the product 12 6 1 5 Connection Details 13 6 1 6 Pump Technical Data 14 7 Installation andelectrical connection Motor Pump coupling system 15 7 1 Installation of bare shaft pump 15 7 2 Installation of the complete pump set 16 8 Commissioning 19 8 1 Cleaning prior to start 20 8 2 Filling and venting 20 8 3 Starting the pump 20 9 Mainte...

Страница 10: ...n to possible problems Information that appears directly on the product such as Rotation direction of flow symbol Identifiers for connections Rating plate Warning stickers must be strictly complied with and kept in a fully legible condition 2 2 Personnel qualifications The installation personnel must have the appropriate qualification for this work 2 3 Danger in event of non observance of the safe...

Страница 11: ...r s scope of supply it is advised to go for CE approved motors panels Environmental safety Disposal of any unwanted scrap material should be disposed in appropriate way so as not to cause any harm to the environment No hazardous material is used in WILO SCP pumps NOTE To avoid ambiguity in the use of the word replace the words replace and renew are used in this manual in the following context Repl...

Страница 12: ... o n g term storage more than 3 month If the equipment will be subject to extended storage condition prior to installation then the manufacturer must be informed about storage duration so that special protection can be recommended Place the SCP pumps horizontally on firm foundation and secure it against falling The pump set must be protected from direct sun light heat dust and frost The rotors or ...

Страница 13: ...temperature min max Mechanicalseal version C Gland packing version C Ambient Temperature Limits of ambient temperature min max C 5 up to 60 Ambient humidity 90 other on request Motor insulation class F other on request Motor protection level IP 55 Electrical protection for motor required in place in accordance with localregulation Acoustic pressure level In accordance with motor performances Refer...

Страница 14: ...e 6 pg 14 For two stage pumps these neckrings are located in the bottom half of the casing by half spigot tung and groove and its rotation is restricted by flat face of the top casing For rest of the single stage pumps plain neck rings with neck ring pins in bottom casing for locking are used The neck ring pin is press fitted in the neck ring 6 1 3 Sealingsystem To prevent leakage along the shaft ...

Страница 15: ...8 29 SCP 200 320 HA 3 8 3 8 3 4 3 8 3 4 3 4 3 4 M8 M8 30 SCP 200 370 HA 3 8 3 8 3 4 3 8 3 4 3 4 3 4 M8 M8 31 SCP 200 360 HB 3 8 3 8 3 4 3 8 3 4 3 4 3 4 M8 M8 32 SCP 200 390 HA 3 8 3 8 1 3 8 3 4 3 4 3 4 M8 M8 33 SCP 200 440 HA 3 8 3 8 1 3 8 3 4 3 4 3 4 M8 M8 34 SCP 200 460 HA 3 8 3 8 1 3 8 3 4 3 4 3 4 M8 M8 35 SCP 200 550 HA 3 8 3 8 1 3 8 1 2 1 2 3 4 M8 M8 36 SCP 200 480 HA 3 8 3 8 1 3 8 1 2 1 2 3 ...

Страница 16: ...0 DS 0 48 17 5 3 4 2 0 6309 2z 6309 2z 28 SCP 200 310 HA 0 50 17 5 3 3 1 75 6308 2z 6308 2z 29 SCP 200 320 HA 0 50 17 5 3 3 1 75 6308 2z 6308 2z 30 SCP 200 370 HA 0 50 17 5 3 3 1 75 6308 2z 6308 2z 31 SCP 200 360 HB 0 53 17 5 3 3 1 75 6308 2z 6308 2z 32 SCP 200 390 HA 0 53 20 3 3 2 05 6311 2z 6311 2z 33 SCP 200 440 HA 0 50 20 3 3 2 05 6311 2z 6311 2z 34 SCP 200 460 HA 0 53 20 3 3 2 05 6311 2z 6311...

Страница 17: ...ectrical motor selection Select an electrical motor with sufficient power margin regarding the motor rating The table below will guide you in this selection Electrical motor selection Shaft power P2 4 KW 4 kW P2 10 kW 10 kW P2 40 kW 40 kW P2 Recommended power margin 25 20 15 10 Example Duty point 100 m3 h 35 m pump efficiency 78 Pump shaft power 12 5 kW Electrical motor rating including margin 12 ...

Страница 18: ...sulation material in order to avoid vibration transmission to the ground CAUTION Risk of material damage Do not hold the pump by the motor module when tightening the screwed connections Apply the wrench surfaces to the suction pressure port inserted It is insufficient to check level on the machined pads of base plate with a spirit level because it is possible that some types of errors will not be ...

Страница 19: ... zero Rotate the coupling by 180 and record the readings on each gauge The readings should be identical though not necessarily zero Either positive or negative readings are acceptable provided they are equally positive or negative Adjust the position of one of the units if necessary Rotate the coupling unit The gauges are to be in the line horizontally and adjust the dial to zero Repeat the operat...

Страница 20: ...wear or leakages Packing should be handled with care and it should not be allowed to pick up the dust or abrasive matter by coming into contact with floors or dirty benches It is bad practice to hammer packing to facilitate the insertion Pumps are dispatched from our works with the stuffing boxes unpacked otherwise packing will be aged The packing is packed with greaseproof paper and dispatched wi...

Страница 21: ...usted in the operating limits of the pump given in the technical data The electrical motors can bedrivenbya frequency converter in order to adapt the pump performances the duty point required Please contact WILO before connecting the frequency converter to the motor to make sure that the electrical motor is compatible with this driver Inany case please informWILOatthe quotation stage ifthe pump se...

Страница 22: ...th a non return foot valve the pump casing and inlet pipe work can be filled with liquid from an external source under pressure The pressure imposed on the pump by this method must not exceed that for which the pump is designed In certain cases priming can be achieved by flooding back from the delivery side of the pump By extracting air or gas from the pump casing To enable this method to be used ...

Страница 23: ...very valve Check that the driving unit is not being overloaded during valve opening Overloading may occur if the pump is discharging into an empty system If the pumping unit fails to generate at least its rated delivery pressure it must be stopped immediately the cause ascertained Check vibration of pump set and ensure that vibration level is within limits specified Check that noise level is withi...

Страница 24: ...echanical seal check that there is no visible leakage For any abnormality observed from the visual manual inspection and through maintenance inspection logs stop the pump and investigate Fault finding Many of the common faults which occur on centrifugal pumps and which can be diagnosed by observations are given in the chart under section 10 Faults causes and remedies Routine maintenance Parts Acti...

Страница 25: ... if the wear rings and the impeller are made with in the same materials of low galling tendencies For materials with higher galling tendencies AISI 304 316 etc higher clearance is provided 0 125 mm to be added to given values Information regarding original design dimensions and clearances is furnished in data sheet Any other information if needed can be requested from Service Department WILO SE Su...

Страница 26: ...Drive End 7 Shaft sleeve 26 Hex plug 8 O ring 27 Air cock 9 Spacer Sleeve 28 Hex screw for jacking 10 Sleeve nut 29 Studs for split flange 11 Stuffing box bush 30 Coupling key 12 Glandpacking 31 Gasket 13 Logging ring 32 Water thrower 14 Gland 33 Steady pin 15 Stud for gland 34 Stud coupling 16 Bearingend cover Drive End 35 Sealingconnection Flushing Pipe 17 Bearing Drive End 36 Hex screw for bear...

Страница 27: ...aft sleeve 26 Hex plug 8 O ring 27 Air cock 9 Spacer Sleeve 28 Hex screw for jacking 10 Sleeve nut 29 Studs for split flange 11 Stuffing box bush 30 Coupling key 12 Mechanical seal 31 Gasket 13 Grab screw 32 Water thrower 14 Glandplate 33 Steady pin 15 Stud for gland 34 Stud coupling 16 Bearingend cover Drive End 35 Sealingconnection Flushing Pipe 17 Bearing Drive End 36 Hex screw for bearing hous...

Страница 28: ...echanical seal The procedure up to water thrower removal is same as per gland pack version Disassembly of mechanical seal isas follows Slide out the gland plate carefully over the shaft Now mark the position of mechanical seal 12 on the shaft 4 to ease the position while reassembling Unscrew the grub screw of the seal adjusting ring Pull the mechanical seal carefully over the shaft followed by rem...

Страница 29: ...g of the O ring 8 Screw the sleeve nut 10 but don t tight it now keep it loose Now slide in the stuffing box bush 11 over the shaft on both sides Place the logging ring 13 next to the stuffing box bush 11 Side in the gland 14 followed by water thrower 32 n both side Now slide the bearing inner cover 16 20 on either side of the shaft 4 Now place the thrust collar 19 followed by thrust end bearing 2...

Страница 30: ... 2 Stationary seat 3 Stationary seat 4 Gland plate 5 O ring 6 Shaft X Mechanical seal 1 6 Abutment ring 1 7 Abutment ring fixing screw 9 5 4 Re assembly of the pump Mechanical seal version pump For assembling mechanical seal version pump follow the same procedure as done for gland pack version pump Difference in assembly of mechanical seal pump is as follows Re assembly of mechanical seal is as fo...

Страница 31: ...with solution 8 Air leaks into pump through stuffing boxes Ensure stuffing box sealing 9 Foot valvetoo smallor leaking Replace I Attend 10 Foot valvepartiallyclogged Clean 11 Inlet of suction pipe insufficiently submerged Ensure adequate submergence such that footvalve is not exposed 12 Water seal pipe clogged Clean or change 13 Logging ring is improperly located instuffing Position logging ring c...

Страница 32: ... Excessive thrust caused by mechanical failure Check pump operation and assembly inside pump or by failure of hydraulic balancing device if any incase of multistage pump etc 42 Excessive grease or oil in antifriction bearing Attend housing or lack of cooling causing excessive bearing temperature 43 Lack of lubrication Provideproper lubrication 44 Improper installation of antifriction bearings Rect...

Страница 33: ...Annexure 1 A Cross sectional Drawing of SCP HA for ref only B Cross sectional Drawing of SCP HB for ref only Installation and operating instructions WILO Split Case Pumps 31 ...

Страница 34: ...C Cross sectional Drawing of SCP DV for ref only D Cross sectional Drawing of SCP DS for ref only Installation and operating instructions WILO Split Case Pumps 32 ...

Страница 35: ...E Cross sectional Drawing of SCP HS for ref only Installation and operating instructions WILO Split Case Pumps 33 ...

Страница 36: ...ing liquid for bearings as specified 10 Free rotation of pump and drive shafts 11 Lubrication of bearings 12 Checking of insulation resistance of motor if supplied by WILO M P 13 Proper cable termination Clients Scope 14 Motor Protection Relay Setting Check with Clients 15 Check all interlocks as specified provided 16 No load trial operation of drive Direction of rotation is ok Noise and vibration...

Страница 37: ...arged 14 Battery cables and lead are available 15 Exhaust silencer and all required exhaust piping is completed 16 Fuel tank is supplied Supply return fuel lines connected to engine 17 Engine coupled with water pump and all discharge piping is completed 18 Lube oil coolant and fuel is available at site 19 Lubrication of bearings 20 Checking of insulation resistance of motor if supplied by WILO M P...

Страница 38: ...e Size Liquid Delivery Pipe Size pH Value Valves Suction Flooded Lift Expansion Joints Pump Operating Parameters Motor Operating Parameters Suction Pressure Current Discharge Pressure Voltage RPM RPM DE Bearing Temperature DE Bearing Temperature NDE Bearing Temperature NDE Bearing Temperature Duration of Trial Run Winding Temperature Max Observations and Remarks Customer Representative WILO M P Re...

Страница 39: ...iquid Delivery Pipe Size pH Value Valves Suction Flooded Lift Expansion Joints Pump Operating Parameters Engine Operating Parameters Suction Pressure RPM Discharge Pressure Oil Pressure RPM Water Temperature DE Bearing Temperature Lubricating Oil Temperature NDE Bearing Temperature Gear Box Temperature Duration of Trial Run Observations and Remarks Auto Mode Manual Mode Customer Representative WIL...

Страница 40: ...Pump set Levelling Record Required accuracy of pump set levelling is 0 05 mm Result Customer Representative WILO M P Representative Installation and operating instructions WILO Split Case Pumps 38 ...

Страница 41: ...ion and Delivery Piping Gap Between Coupling Halves mm Actual Gap mm B After Connecting Suction and Delivery Piping Gap Between Coupling Halves mm Actual Gap mm Customer Representative WILO M P Representative Installation and operating instructions WILO Split Case Pumps 39 ...

Страница 42: ...ent at Pump House Floor Noise Level in dBA A B C D Background Noise dBA Instrument Details Distance 1 Mtr from the Pump Make Model Sr No Customer Representative WILO M P Representative Installation and operating instructions WILO Split Case Pumps 40 ...

Страница 43: ...rement Pk to Pk Sr No Position V H A Displacement Velocity mm sec Displacement Velocity mm sec Displacement Velocity mm sec 1 Pump DE 2 Pump NDE 3 Motor DE 4 Motor NDE Instrument Details Make Model Sr No Customer Representative WILO M P Representative Installation and operating instructions WILO Split Case Pumps 41 ...

Страница 44: ...ump Type Make Project Bearing Temperature Sr No Position Temperature Ambient Temperature Remarks 1 Pump DE 2 Pump NDE 3 Motor DE 4 Motor NDE Instrument Details Make Model Sr No Customer Representative WILO M P Representative Installation and operating instructions WILO Split Case Pumps 42 ...

Страница 45: ...NOTES ...

Страница 46: ...______________________________________________________ WILO Mather and Platt Pumps Private Ltd Mumbai Pune Road Chinchwad Pune 411 019 Maharashtra India Tel 91 20 27442100 1 2 3 4 Toll Fee Service 1 800 266 8866 Fax 91 2027442111 service in wilo com www wilo in ...

Отзывы: