Wenger 145V006 Скачать руководство пользователя страница 4

4

1. Check the level of the 

entire floor where the 

cabinets will be 

installed. Determine 

the highest point of 

the floor in that area.

Extend all levelers 

until the bottom of the 

cabinet will be higher 

than the highest point 

in the floor.

2. Adjust the levelers on 

one side until the front 

edges of the cabinet 

side panels are plumb 

(side-to-side).

3. Measure A and B with a tape 

and adjust the front levelers 

until A=B (+

1

/

32

inch).

4. Adjust both front levelers 

equally until the front 

edges of the cabinet are 

plumb (front-to-back).

5. Recheck that A=B. 

Readjust if necessary 

(repeat steps 2-4).

If additional cabinets will be installed:

6. Adjust the levelers on the next cabinet so it

will line up with the top of the first cabinet.

7. Repeat steps 2-5 for the second cabinet.

8. Continue in the same manner until all cabinets

are leveled.

L

EVELING THE

C

ABINETS

NOTE:

Do not try to level the cabinets to match soffits.

NOTE:

Do not try to plumb the cabinet to match adjacent walls.

NOTE:

For proper door alignment, follow these instructions carefully.

NOTE:

To access the levelers, the file drawers must be removed first. 

See “File Drawer Removal” before leveling the cabinet.

Содержание 145V006

Страница 1: ...ration using the information below CONTENTS Wenger Corporation 2014 Printed in USA 08 14 Part 145V345 04 Wenger Corporation 555 Park Drive P O Box 448 Owatonna Minnesota 55060 0448 Questions Call USA...

Страница 2: ...direct indirect special incidental or consequential damages resulting from the use or defect of this manual The information in this document is not intended to cover all possible conditions and situa...

Страница 3: ...t approximately in their final position Remove all items from the hardware bag and determine where all of the fasteners will be used Screw Insert 1 4 20 x 5 8 FASTENER PARTS LIST Note Hardware Pack ma...

Страница 4: ...ont edges of the cabinet are plumb front to back 5 Recheck that A B Readjust if necessary repeat steps 2 4 If additional cabinets will be installed 6 Adjust the levelers on the next cabinet so it will...

Страница 5: ...ogether before attaching them to the back wall 1 Using the Cabinet Connector Brackets the cabinets can be tied together and to the wall surface at the top The brackets have extra holes if the cabinets...

Страница 6: ...desired shelf heights The flat edge of the Shelf Support should face up to match the slots in the bottom of the shelf 2 Install the shelves 3 The larger shelf uses six Shelf Supports and is to be plac...

Страница 7: ...wers can be removed by pulling outward Now the cabinet can be leveled according to Leveling the Cabinets 2 Re install the file drawers by aligning the rails that are attached to the file drawer with t...

Страница 8: ...8 This page is intentionally blank...