Using a tape measure, position the half center hinges equally spaced in between the center 

hinges and the graduated end hinges. Position the holes of the lower hinge leaf at the top 

rail of the Intermediate section. Using the half center hinge as a template, drill pilot holes, 1” 

deep into the Intermediate section with a 1/8” drill bit (if needed).

IMPORTANT: 

BE EXTREMELY CAREFUL NOT TO DRILL THRU THE SECTION. ONLY DRILL 1” 

DEEP.
Attach the lower hinge leaf of the center hinge to the Intermediate section using (2) 1/4” - 14 

x 1” lag screws. Repeat for other half center hinge(s).
If you have single graduated end hinges, insert a short stem track roller / short stem tandem 

track roller (if included) into the hinge tube on each side.
If you have double graduated end hinges, insert a long stem track roller / short stem tandem 

track roller (if included) into the hinge tubes on each side.

IMPORTANT: 

WHEN PLACING TRACK ROLLERS / TANDEM TRACK ROLLER (IF INCLUDED) 

INTO GRADUATED END HINGES NUMBER 2 AND HIGHER, THE TRACK ROLLER / TANDEM 

TRACK ROLLER (IF INCLUDED) GOES INTO TUBE FURTHEST AWAY FROM SECTION.

Attaching Top Fixtures And Strut To Top Sec-

tion

 

7

 

NOTE:

 Refer to door section identification, located in the pre-installation section of this 

manual to determine what size section you need to use as your top section. Measure your 

section to make sure it is the correct height as indicated on the chart.
Place the top section face down on a couple of sawhorses or flat clean/ smooth surface. 

Lay a 

SHORT STRUT

 onto the top rail of the top section. Position the top of the strut 3/4” 

downward from the top edge of the top section. Center the short strut from side to side on 

the section surface. Drill pilot holes, 1” deep into the top section using a 1/8” drill bit.

IMPORTANT: 

BE EXTREMELY CAREFUL NOT TO DRILL THRU THE SECTION. ONLY DRILL 1” 

DEEP.
Attach the strut using (1) 1/4” - 14 x 1” lag screw at each pre-drilled hole.

NOTE:

 If your door came with two top fixtures, then one top fixture and a short stem track 

roller are required for each side.

NOTE:

 If your door came with four top fixtures, then two top fixtures and a long stem track 

roller are required for each side.
Loosely secure the top fixture slide and the “L” reinforcement bracket (if applicable) to the top 

fixture base using (1) 5/16” - 18 x 3/4” carriage bolt and (1) 5/16” - 18 hex nut, as shown. 

Repeat for other top fixture assemblies.
Starting on the left hand side, align the lip of the top fixture base onto the top corner of the 

top section and even with the side edge of the top section. Using the top fixture base as a 

template, mark and pre-drill (3) 9/32” diameter holes through the top section.

NOTE:

 If the “L” reinforcement bracket(s) was not supplied with your door, then only pre-drill 

(2) 9/32” diameter holes drilled holes are needed. Along with only (2) 1/4” - 20 x 2-1/4” 

carriage bolts and (3) 1/4” - 20 flange hex nuts used to attach the top fixture assembly to the 

top section.
Attach the top fixture base to the top section using 1/4” - 20 x 2-1/4” carriage bolts and 1/4” 

- 20 flange hex nuts. Repeat the same process for the right hand side.

IF YOU HAVE FOUR TOP FIXTURE ASSEMBLIES:

 Position the second top fixture assembly 

next to the first installed top fixture assembly. Using the top fixture base as a template, drill 

pilot holes, 1” deep into the top section with a 1/8” drill bit (if needed).

IMPORTANT: 

BE EXTREMELY CAREFUL NOT TO DRILL THRU THE SECTION. ONLY DRILL 1” 

DEEP.

NOTE:

 If the “L” reinforcement bracket(s) was not supplied with your door, then only pre-drill 

(2) 1/8” diameter holes drilled holes are needed.
Attach the top fixture base to the top section using 1/4” - 14 x 1” lag screws. Repeat the 

same process for the right hand side.

Positioning Bottom Section

 

8

 

Center the bottom section in the door opening. Level the section using wooden shims (if 

necessary) under the bottom section. When the bottom section is leveled, temporarily hold it 

in place by driving a nail into the jamb and bending it over the edge of the bottom section on 

both sides.

Attaching Vertical Tracks To Jambs

 

9

 

NOTE:

 Depending on your door, you may have Fully Adjustable Flag Angles, Riveted Vertical 

Track Assemblies or you may have Angle Mount Vertical Track Assemblies. Refer to Package 

Contents / Breakdown of Parts, to determine which Flag Angles / Vertical Track Assemblies 

you have.

IMPORTANT: 

IF YOUR DOOR IS TO BE INSTALLED PRIOR TO A FINISHING CONSTRUCTION 

OF THE BUILDING’S FLOOR, THE VERTICAL TRACKS AND THE DOOR BOTTOM SECTION 

ASSEMBLY SHOULD BE INSTALLED SUCH THAT WHEN THE FLOOR IS CONSTRUCTED, NO 

DOOR OR TRACK PARTS ARE TRAPPED IN THE FLOOR CONSTRUCTION.

IMPORTANT: 

THE TOPS OF THE VERTICAL TRACKS MUST BE LEVEL FROM SIDE TO SIDE. 

IF THE BOTTOM SECTION WAS SHIMMED TO LEVEL IT, THE VERTICAL TRACK ON THE 

SHIMMED SIDE MUST BE RAISED THE HEIGHT OF THE SHIM.

NOTE:

 Make sure the counterbalance lift cable is located between the track rollers and the 

door jamb.
Starting on the left hand side of the bottom section, remove the nail. Position the left hand 

vertical track assembly over the track rollers of the bottom section and install, as shown. Drill 

3/16” pilot holes into the door jamb for the lag screws.

FOR FULLY ADJUSTABLE FLAG ANGLES:

 Loosely fasten jamb brackets and flag angle to 

the jamb using 5/16” x 1-5/8” lag screws. Tighten lag screws, securing the bottom jamb 

bracket to jamb, maintain 3/8” to 5/8” spacing, between the bottom section and vertical 

track. Hang counterbalance lift cable over flag angle. Repeat same process for other side.

FOR RIVETED VERTICAL TRACK ASSEMBLY:

 Loosely fasten jamb brackets and flag angle 

to the jamb using 5/16” x 1-5/8” lag screws. Tighten lag screws, securing the bottom jamb 

bracket to jamb, maintain 3/8” to 5/8” spacing as shown between the bottom section and 

vertical track. Hang counterbalance lift cable over flag angle. Repeat same process for other 

side.

FOR ANGLE MOUNT VERTICAL TRACK ASSEMBLY:

 Loosely fasten the slots in the wall 

angle to the jamb using 5/16” x 1-5/8” lag screws. Tighten lag screws, securing the bottom 

slot in the wall angle, maintain 3/8” to 5/8” spacing as shown between the bottom section 

and vertical track. Hang counterbalance lift cable over angle mount. Repeat same process for 

other side.

Stacking Sections

 

10

 

NOTE:

 Refer to door section identification, located in the pre-installation section of this 

manual to determine what size sections you need to use as your intermediate I (second) 

section and intermediate II (third) section (if applicable). Measure your sections to make sure 

they are the correct height as indicated on the chart.

NOTE:

 Make sure graduated end and center hinges are flipped down, when stacking another 

section on top.
With assistance, lift second section and guide the track rollers into the vertical tracks. Keep-

ing the sections vertically aligned, lower section until it is seated against bottom section.

FOR CENTER HINGE(S) AND OR HALF CENTER HINGE(S):

 Flip a upper hinge leaf up and 

use it as a template. Mark and pre-drill (2) 1/8” pilot holes, 1” deep into the section with a 

1/8” drill bit.

IMPORTANT: 

BE EXTREMELY CAREFUL NOT TO DRILL THRU THE SECTION. ONLY DRILL 1” 

DEEP.
Attach the center hinge upper leaf to the section using (2) 1/4” - 14 x 1” lag screws. Repeat 

same process for other center hinge(s) and or half center hinge(s).

FOR GRADUATED END HINGES:

 Starting with the outer graduated end hinges, flip the 

upper hinge leaf up and use it as a template. Mark and pre-drill (2) 9/32” diameter holes 

through the section. Attach the upper hinge leaf to the section using (2) 1/4” - 20 x 2-1/4” 

carriage bolts and (2) 1/4” - 20 flange hex nuts. Repeat same process for the other side.

IF YOU HAVE DOUBLE GRADUATED END HINGES:

 Flip the inner upper hinge leaf up and 

use it as a template. Mark and pre-drill (2) 1/8” pilot holes, 1” deep into the section with a 

1/8” drill bit.

IMPORTANT: 

BE EXTREMELY CAREFUL NOT TO DRILL THRU THE SECTION. ONLY DRILL 1” 

DEEP.
Attach the inner upper hinge leaf to the section using (2) 1/4” - 14 x 1” lag screws. Repeat 

same process for the other side.

IMPORTANT: 

PUSH & HOLD THE HINGE LEAFS SECURELY AGAINST THE SECTIONS WHILE 

SECURING WITH APPROPRIATE FASTENERS. THERE SHOULD BE NO GAP BETWEEN THE 

HINGE LEAFS AND THE SECTIONS.
Repeat same process for other sections (if applicable), except top section.

Stacking Top Section

 

11

 

Place the top section in the opening. Install a nail to prevent the top section from falling 

backwards. Now, flip up the hinge leaves, hold tight against section, and fasten center hinges 

first and end hinges last (refer to step, Stacking Sections). Vertical track alignment is critical. 

Position flag angle or wall angle between 1-11/16” (43 mm) to 1-3/4” (44 mm) from the 

edge of the door; tighten the bottom lag screw. Flag angles must be parallel to the door sec-

tions. Repeat for other side.

IMPORTANT: 

THE DIMENSION BETWEEN THE FLAG ANGLES OR WALL ANGLES MUST BE 

DOOR WIDTH PLUS 3-3/8” (86MM) TO 3-1/2” (89 MM) FOR SMOOTH, SAFE DOOR OPERA-

TION.

FOR FULLY ADJUSTABLE TRACK OR RIVETED TRACK:

 Complete the vertical track instal-

lation by securing the jamb bracket(s) and tightening the other lag screws. Push the vertical 

track against the track rollers so that the track rollers are touching the deepest part of the 

curved side of the track; tighten all the track bolts and nuts. Repeat for other side.

FOR ANGLE MOUNT TRACK:

 Complete the vertical track installation by securing the jamb 

bracket(s) and or tightening the other lag screws. Push the vertical track against the track 

rollers so that the track rollers are touching the deepest part of the curved side of the vertical 

track, as shown. Repeat for other side.

6

Содержание Torsion 7100 Series

Страница 1: ...arage Door 12 Operation And Maintenance 12 Warranty 13 Wayne Dalton a division of Overhead Door Corporation Model 7100 Series T o r s i o n Quick Start Guide Residential and Light Commercial Standard...

Страница 2: ...t information 18 For windloaded doors the wind performance is achieved via the entire door system and component substitution is not authorized without express permission by Wayne Dalton NOTE It is rec...

Страница 3: ...d and Right Hand Cable Drums J5 Center Bracket As Required J6 Center Bearing As Required J7 Torsion Shaft Torsion Keyed Shaft As Required J8 Torsion Keyed Shafts As Required J9 Keys As Required J10 Ce...

Страница 4: ...ation section of this manual or refer to Breakdown of Parts With the bottom section facing down from the previous step uncoil the counterbalance lift cables NOTE Refer to Package Contents Breakdown of...

Страница 5: ...CK ROLLER IF INCLUDED GOES INTO TUBE FURTHEST AWAY FROM SECTION Attaching Hinges and Strut To Intermediate Section s 6 NOTE Refer to door section identification located in the pre installation section...

Страница 6: ...SECTION WAS SHIMMED TO LEVEL IT THE VERTICAL TRACK ON THE SHIMMED SIDE MUST BE RAISED THE HEIGHT OF THE SHIM NOTE Make sure the counterbalance lift cable is located between the track rollers and the d...

Страница 7: ...INED FROM INSIDE THE BUILDING LOOKING OUT NOTE End bearing brackets are right and left hand DEPENDING ON WHICH END BEARING BRACKET YOU HAVE Either attach the left hand end bearing bracket to the left...

Страница 8: ...and left hand by the set screw color IF YOU DON T HAVE A COUPLER ASSEMBLY Facing the inside of the door lay the torsion shaft torsion keyed shaft on the floor Lay the torsion spring with the black win...

Страница 9: ...kets If your spring diameter is either 2 or 2 5 8 then two springs will share the same center bracket unless a coupler assembly is provided IF YOU DON T HAVE A COUPLER ASSEMBLY Slide center bracket be...

Страница 10: ...ical tracks just above the third track roller This is to prevent the garage door from rising while winding springs NOTE Check the following before attempting to wind torsion spring s a Counterbalance...

Страница 11: ...LOCKING PLIERS FROM VERTICAL TRACKS Raise the door until the top section and half of the next section are in the horizontal track radius Do not raise door any further since rear of horizontal tracks a...

Страница 12: ...ter pins clevis pins are under HIGH SPRING TENSION Adjustments and repairs must only be made by a trained door systems technician using proper tools and instructions DO NOT REMOVE COVER OR PAINT OVER...

Страница 13: ...s door located as spelled out in the installation instructions even if the door is motor operated Failure to install and use these lift handles gripping points on this door can result in serious injur...

Страница 14: ...after discovery within the applicable warranty period and in writing to the Seller whose name and address appear below The purchaser must allow Seller a reasonable opportunity to inspect any Product c...

Страница 15: ......

Страница 16: ...rvice representative They will be happy to handle any questions that you may have Thank you for your purchase PLEASE DO NOT RETURN THIS PRODUCT TO THE STORE After installation is complete leave this I...

Отзывы: