Setting the Float Control Valve
Opening and Closing Speed
– Turn the adjustment screws on the Closing Speed and Opening Speed Controls, if the main valve is so
equipped, OUT, counterclockwise, 1½ to 2½ turns from full closed position.
STEP 1
To ensure proper operation, any trapped air will need to be bled
off the valve cover during startup. The ACV includes a bleed valve,
use a flat head screwdriver to slowly open the valve (See Figure
1).
STEP 2
Pressure the line, by opening the upstream isolation valve slowly.
Air is vented through the air bleed valve. Tighten the fitting when
liquid begins to vent (See Figure 1).
Globe
Angle
Size (in)
1
1/4
1
1/2
2
21/2
3
4
6
8
10
12
14
16
20
24
A (in)
16
16
20
22
22
24
32
34
38
44
48
52
56
56
B (in)
10
10
12
14
14
16
24
26
28
30
34
40
48
48
Size (in)
1
1/4
1
1/2
2
2
1/2
3
4
6
8
10
12
14
16
C (in)
16
16
20
22
22
24
32
34
38
44
48
52
D (in)
10
10
12
14
14
16
24
26
28
30
34
40
Counterclockwise to OPEN
bleed valve
The following tables detail the recommended minimum valve servicing dimensions.
A
B
C
FLOW
FLOW
FLOW
D
FLOW
Valve Servicing Dimensions
Figure 1
Position Indicator
IOM-ACV-110-14_6110-14-4" 2115
EDP# 1917107
© 2021 Watts 3