Installation Guidelines

NOTICE

 

The flange gasket bolts for the gate valves should be 

retightened during installation as the bolts may have  

loosened due to storage and shipping.

1.  Consult local codes for specific installation requirements and 

restrictions applicable to your area. At least 20 psi (138 kPa) is 

recommended for system supply pressure.

2.  Install the valve assembly only in the orientation or flow direction 

shown. The gate valves may be rotated as permitted by the 

flange bolt pattern.

NOTICE

 

 Normal discharge and nuisance spitting are accommodated by 

use of a FEBCO

®

 air gap fitting and a fabricated indirect waste 

line. The gap drain is not designed to catch the maximum dis-

charge possible from the relief valve. The installation of a FEBCO 

air gap with the drain line terminating above a floor drain handles 

any normal discharge or nuisance spitting through the relief valve. 

However, floor drain size may need to be designed to prevent 

water damage caused by a complete failure condition. Do not 

reduce the size of the drain line from the air gap fitting.
When installing an air gap, attach the air gap brackets directly 

onto the flood sensor.
3.  Install the valve assembly where it is accessible for periodic 

testing and maintenance. Clearances shown in the installation 

views apply to exterior, interior, and pit or vault installations  

and are only recommendations. (See Figures 1 and 2.) These 

minimums do not apply to removable protective enclosures. 

Refer to local codes for actual requirements in the area.

4.  Before installing the valve into the line, flush the supply line of 

all foreign material. Failure to flush the supply line may cause 

the check valves to become fouled and require disassembly 

and cleaning.

5.  Lift the assembly by connecting lift hooks to the lift rings cast 

into the valve body. Do not lift the assembly by connecting to 

the gate valve handwheels or stems. Use of the optional valve 

setters (horizontal units only) provides for a rigid connection to 

the supply line (with the correct centerline) without the need for 

concrete thrust blocks. 

6.  For vertical installation, follow this procedure:

•  Loosen the bolts on the groove coupling just enough to 

allow rotation of the outlet check.

•  Remove the hose from the inlet of the bypass meter, being 

sure to remove and save the gasket.

•  Rotate the outlet check 180° to the vertical position and 

install pipe support (to be furnished by the customer and 

shall fit the same size pipe as the valve being installed, 

except 21/2" valves require a 3" pipe support) on the pipe 

support lug that is now positioned under the check.  

(See Figure 2.)

•  Retighten and inspect groove coupling.
•  Reattach the hose to the inlet of the bypass meter, being 

sure to include the gasket removed previously, and ensuring 

meter is oriented with the face plate up. If necessary, adjust 

the bypass piping to connect the bypass hose by loosening 

the nuts on the bulkhead fittings that attach the bypass to 

the valve body and rotating the piping. Retighten the bulk-

head nut once the piping is in place.

NOTICE

 

It may be desirable to move the bypass mounting bracket based 

on the location of the valve. The bypass mounting bracket can 

be moved to the opposite side. Follow the preceding instructions 

for rotating the bypass piping to accommodate the new position. 

NOTICE

 

The valve body and pipe support are intended to support the 

weight of the second check valve and outlet gate valve only. The 

piping above the outlet gate valve must be supported indepen-

dently. Retighten the bolts of the groove coupling. Rotate the 

outlet gate valve as desired or required.

7.  (For vertical installation) Remove the formed tube from the 

bypass piping, then repeat step 6. Upon completion, rotate 

the compression fitting elbow 180º and reinstall the tube, 

rotating the pipe tee now at the bottom of the outlet check to 

align with tube.

8.  After installation, slowly fill the assembly with water and bleed 

air from the body using test cocks No. 3 and No. 4. Test the 

valve assembly to ensure correct operation.

NOTICE

 

All assemblies are tested at the factory for proper operation and 

leakage. If the valve does not pass the field test, it is most likely 

due to a fouled check valve. This is not covered by the factory 

warranty. The valve cover(s) must be removed and the check 

seats inspected and cleaned. Any damage or improper operation 

caused by pipeline debris or improper installation or start-up is 

not included in the factory warranty. In case of a possible war-

ranty claim, contact the local supplier or FEBCO representative. 

Do not remove the valve assembly from the pipeline.
9.  Protect the assembly from freezing and excessive pressure 

increases. Pressure increases can be caused by thermal 

expansion or water hammer. These excessive pressure situa-

tions must be eliminated to protect the valve and system from 

possible damage.

Содержание FEBCO 880V Series

Страница 1: ...led by a licensed contractor in accordance with local codes and ordinances IS F 880V RP RPDA FS Installation Maintenance and Repair Manual Series 880V LF880V FS and LF886V FS Reduced Pressure Zone Assemblies Reduced Pressure Detector Assemblies 21 2 10 In this trio of MasterSeries assemblies LF880V FS and LF886V FS are each equipped with an integrated flood sensor that detects excessive relief val...

Страница 2: ...he outlet check 180 to the vertical position and install pipe support to be furnished by the customer and shall fit the same size pipe as the valve being installed except 21 2 valves require a 3 pipe support on the pipe support lug that is now positioned under the check See Figure 2 Retighten and inspect groove coupling Reattach the hose to the inlet of the bypass meter being sure to include the g...

Страница 3: ...uld be pushed away from the body approximately 1 4 inch 3 Inspect the parts and clean debris from the disc and seat ring Replace worn or damaged parts as required 4 Replace the cover making sure the spring assembly is posi tioned in the pivot socket If necessary apply FDA Approved grease to the O ring groove in the body to keep the O ring in position while installing the cover 5 Install the bolts ...

Страница 4: ...N DURATION TO ONE YEAR FROM THE DATE OF ORIGINAL SHIPMENT PROBLEM CAUSE SOLUTION Continuous relief valve discharge Debris on check seating surfaces Disassemble and clean Debris on relief valve surfaces Intermittent relief valve discharge Inlet pressure fluctuations Eliminate fluctuations Downstream pressure surges Eliminate surges Troubleshooting Add on and Retrofit Sensor Connection Kits for Buil...

Страница 5: ...cter les codes et les ordonnances locaux IS F 880V RP RPDA FS Manuel d installation d entretien et de réparation Série 880V LF880V FS et LF886V FS Ensembles pour zones à pression réduite Dispositifs de pression réduite 21 2 po à 10 po 6 4 cm à 25 4 cm Les modèles de série MasterSeries LF880V FS et LF886V FS sont tous deux équipés d un capteur d inondation intégré qui détecte les décharges excessiv...

Страница 6: ...t d étanchéité Tournez le clapet antiretour de sortie à 180 à la position verticale et installez le support de tuyau à fournir par le client et doit s adapter à la même grosseur que la valve installée sauf pour les vannes de 21 2 po 6 4 cm qui nécessitent un support de tuyau de 3 po 7 6 cm sur la languette de soutien du tuyau qui est maintenant positionnée sous l antiretour Voir la figure 2 Resser...

Страница 7: ...nus et le couvercle doit être éloigné à environ 1 4 po du corps 3 Inspectez les pièces et nettoyez les débris du disque et de la bague de siège Remplacez les pièces usées ou endommagées au besoin 4 Replacez le couvercle en vous assurant que le ressort est positionné dans l emboîture du pivot Au besoin appliquez de la graisse approuvée par la FDA sur la rainure du joint torique sur le corps afin de...

Страница 8: ...z et nettoyez Débris sur les surfaces de la soupape de décharge Décharge intermittente de la soupape de décharge Fluctuations de pression d entrée Éliminez les fluctuations Surtensions de pression en aval Éliminez les surtensions Dépannage Trousses de connexion de capteur complémentaire et de modernisation pour les systèmes de gestion de bâtiment N DE PIÈCE TROUSSE COMPLÉMENTAIRE DE MODERNISATION ...

Страница 9: ...be instalar este producto de acuerdo con los reglamentos y las disposiciones locales IS F 880V RP RPDA FS Manual de instalación mantenimiento y reparación Serie 880V LF880V FS y LF886V FS Válvulas antirretorno de principio de presión reducida Conjuntos de detectores de presión reducida 21 2 10 6 3 cm a 25 4 cm En este trío de conjuntos MasterSeries LF880V FS y LF886V FS están equipados con un sens...

Страница 10: ...stale el soporte de la tubería que debe proporcionar el cliente y debe encajar en la tubería del mismo tamaño que la válvula que se instala excepto que las válvulas de 21 2 6 3 cm requieren un soporte de tubería de 3 7 6 cm en la lengüeta de soporte de la tubería que ahora está colocada debajo de la retención Consulte la figura 2 Vuelva a apretar e inspeccione el acoplamiento de ranura Vuelva a co...

Страница 11: ...debe empujarse hacia fuera del cuerpo aproximadamente 1 4 de pulgada 3 Inspeccione las piezas y limpie los residuos del disco y el anillo del asiento Sustituya las piezas desgastadas o dañadas según sea necesario 4 Vuelva a colocar la cubierta asegurándose de que el ensamble del resorte esté colocado en el conector del pivote Si es necesario aplique grasa aprobada por la FDA a la ranura de la junt...

Страница 12: ...ol Desensamble y limpieza Residuos en las superficies de la válvula de alivio Descarga intermitente de la válvula de alivio Fluctuaciones de la presión de entrada Elimine las fluctuaciones Sobretensiones de presión aguas abajo Eliminar sobretensiones Solución de problemas Kits de conexión de sensor de complemento y retroadaptación para sistemas de gestión de edificios NÚMERO DE PARTE KIT ADICIONAL...