Commissioning the Pump Control Valve

STEP 1

NOTE:

 System needs to be filled, pressurized, and ready for flow. Due to an internal system check feature, Automatic Control Valve will 

not flow until pump starts.

Pre-set pilots as noted:

Opening and Closing Speed

 – Prior to pump start, actuate manual operator on solenoid to enable diaphragm assembly to stroke 

open and closed. Observing the limit switch stem indicator, monitor rate of opening and closing speed. Adjust accordingly per applica-
tion requirements.  

NOTE: 

Cycle diaphragm multiple times to confirm rate of movement and remove excess air trapped within the cover chambers (See 

Figure 1 Below).

To increase the rate of opening/closing, turn the adjustment 
screws on the speed controls OUT, counterclockwise (See Figure 
2B Following Page). To decrease the rate of opening/closing, turn 
the adjustment screws on the speed controls IN, clockwise (See 
2A Following Page).

STEP 2

Prior to pump start, energize the solenoid to confirm connection 
to power source.

STEP 3

De-energize the solenoid prior to initial pump start.

STEP 4 

Energize the solenoid at pump start to open the main valve, 
checking that the main valve opens.

Globe

Angle

Size (in)

2

21/2

3

4

6

8

10

12

14

16

20

24

A (in)

20

22

22

24

32

34

38

44

48

52

56

56

B (in)

20

22

22

25

36

38

40

44

48

50

50

50

Size (in)

2

2

 

1/2

3

4

6

8

10

12

14

16

C (in)

20

22

22

24

32

34

38

44

48

52

D (in)

20

22

22

25

36

38

40

44

48

50

Figure 1 

4-Way Solenoid

Manual  

Operation

Normal  

Operation

Содержание AMES 980-16GD

Страница 1: ...Control Valve 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to the information provide...

Страница 2: ...valve into service in a controlled manner to protect the system from damaging over pressure Operation The Pump Control Valve is designed to minimize the surges associ ated with the starting and stoppi...

Страница 3: ...mes to confirm rate of movement and remove excess air trapped within the cover chambers See Figure 1 Below To increase the rate of opening closing turn the adjustment screws on the speed controls OUT...

Страница 4: ...n valve de energize the solenoid checking that the main valve closes STEP 5 STEP 7 Closing Speed Flow Adjustment While free flow goes into the upper chamber the closing speed flow control restricts fl...

Страница 5: ...specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm...

Страница 6: ...in Valve will not close Closed isolation valves in pilot system Check isolation valves ensure open Diaphragm is damaged Conduct diaphragm seal test repair and replace if necessary Main valve stem asse...

Страница 7: ...move cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require...

Страница 8: ...posits and inspect for excessive wear Remove any mineral build up from other components with wire brush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Insp...

Страница 9: ...for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrity of the Seat Seal by following the Seat Seal Test procedure in previous section 12 Retur...

Страница 10: ...3 and Smaller ASTM A276 302 Stainless Steel 13A Bearing Retaining Ring 4 and Larger ASTM A276 302 Stainless Steel 14 Inner Bearing ASTM A276 304 Stainless Steel 15 O ring Buna N Nitrile 16 O ring Buna...

Страница 11: ...IOM A ACV 980 16_680 16 2115 EDP 1917100 2021 Watts 11 NOTES...

Страница 12: ...021 Watts USA Backflow T 978 689 6066 F 978 975 8350 AmesFireWater com USA Control Valves T 713 943 0688 F 713 944 9445 AmesFireWater com Canada T 888 208 8927 F 905 481 2316 AmesFireWater ca Latin Am...

Отзывы: