background image

Issue

Possible Cause

Corrective Action

Notes

Main Valve will not 
open

Closed isolation valves in pilot system.

Check isolation valves, ensure 
open. 

Insufficient supply pressure.

Check upstream pressure.

Depending on water 
source, supply pressure 
may not be controlled by 
valve operator.

Main valve stem assembly corroded/
damaged

Inspect stem assembly, clean/
replace if necessary.

Blockage in pilot system.

Inspect & clean any installed 
pilot system strainers, check 
orifice/speed controls for 
blockages.

Missing fixed orifice assembly.

Verify installation of orifice; 
replace if required/missing. 

Pilot valve inlet isolation 
valve can be used as a 
makeshift orifice assembly 
by partially opening from 
full closed position. 

Improperly configured opening speed 
control (if equipped). 

Adjust opening speed control 
to verify functionality, adjust as 
required.

Standard setting for open-
ing speed control is 1 1/2 
- 2 1/2 turns open from full 
closed position. Can be 
adjusted in field. 

Main Valve will not 
close

Closed isolation valves in pilot system

Check isolation valves, ensure 
open. 

Diaphragm is damaged

Conduct diaphragm seal test, 
repair and replace if necessary. 

Main valve stem assembly corroded/
damaged.

Inspect stem assembly, clean/
replace if necessary.

Blockage in main valve.

Perform freedom of movement  
test; if valve does not close,  
disassemble and remove  
blockage.

Worn/damaged valve seat. 

Perform  seat sealing check; 
disassemble and inspect/repair 
seat if required.

Solenoid will not 
actuate

Possible Cause: Low or no voltage

Check voltage at the solenoid 
connection, insuring that it has 
the minimum of 85% of the 
coils rated voltage.

Should be performed by 
licensed electrician

Troubleshooting Guide

 

6          IOM-A-ACV-920-15_620-15   2115 

EDP# 1917048 

© 2021 Watts

IOM-A-ACV-920-15_620-15   2115 

EDP# 1917048 

© 2021 Watts         7

Содержание Ames 620GD-15

Страница 1: ...Setting the Pressure Controls 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to the inf...

Страница 2: ...the upstream zone The valve will close if necessary until upstream pressure is above the pilot setting The valve should be specified to include the optional opening speed control and position indicato...

Страница 3: ...ed air by loosening a fitting on the valve or a plug at the highest point of the valve as sembly STEP 5 Pressure the line by opening the upstream isolation valve slowly Air is vented through the air b...

Страница 4: ...valve until the inlet pressure drops to the desired setting Fine tune the Reducing Control adjustment to the pressure reduc ing setpoint as detailed in Step 7 STEP 10 Adjust the Sustaining Control sc...

Страница 5: ...counterclockwise increasing the rate of closing IF INSTALLED Opening Speed Flow Control Adjustment The Opening speed flow control allows free flow into the cover and re stricted flow out of the cover...

Страница 6: ...specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm...

Страница 7: ...djust opening speed control to verify functionality adjust as required Standard setting for open ing speed control is 1 1 2 2 1 2 turns open from full closed position Can be adjusted in field Main Val...

Страница 8: ...move cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require...

Страница 9: ...rush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are thread...

Страница 10: ...ts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrit...

Страница 11: ...el 9 Stem Washer ASTM A276 304 Stainless Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iro...

Страница 12: ...resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances over which the Company has no cont...

Отзывы: