CHAPTER 6. MAINTENANCE
6.1 MAINTENANCE SCHEDULE
The Innovation Hot Water Boiler requires regular routine maintenance to ensure continued
reliable operation throughout the service life of the unit. For optimum operation, AERCO
recommends that the following routine maintenance procedures be performed in the time periods
specified in Table 6-1.
Appendix I contains a list of the recommended spare parts for maintenance of the Innovation
Heater.
--WARNING! -
TO AVOID PERSONAL INJURY, PRIOR TO SERVICING ENSURE THAT
THE FOLLOWING GUIDELINES ARE STRICTLY OBSERVED:
•
DISCONNECT THE AC SUPPLY BY TURNING OFF THE SERVICE
SWITCH AND AC SUPPLY CIRCUIT BREAKER.
•
SHUT OFF THE GAS SUPPLY AT THE MANUAL SHUT-OFF VALVE
PROVIDED WITH THE UNIT
•
ALLOW THE UNIT TO COOL TO A SAFE WATER TEMPERATURE TO
PREVENT BURNING OR SCALDING
Table 6-1 - Maintenance Schedule
Section
Item
6 Mos.
12 Mos.
24 Mos.
Labor
Time
6.2
Igniter-Injector
(Kit P/N
58023
)
*Inspect
Inspect
Replace
15 min.
6.3
Flame Detector
(Kit P/N
24356-2
)
*Inspect
Inspect
Replace
15 min.
6.4
Combustion Calibration
*Check
Check
1 hr.
6.5
Testing of Safety Devices
Test
20 min.
6.6
Fireside Inspection
Inspect &
Clean
2 hrs.
6.7
Waterside Inspection
*Inspect
Inspect
1 hr.
6.8
Heat Exchanger Cleaning
Inspect & Clean
(as required)
-
2 hrs.
6.9
Condensate Drain Trap
*Inspect
Inspect & Clean
-
30 min.
6.10
Air Filter
(P/N
59138
)
Clean or
Replace
-
5 min.
6.13
Low Water Cutoff (LWCO)
Probe Capacitor (Kit P/N
69126
)
-
Test
Replace &
Test
15 min.
*
Only performed after initial 6 month period after initial startup.