Identify a suitable mounting location for the Warmup Manifold.
The location should meet the following requirements;
•
The surface on to which it is to be mounted should be:
•
Structurally sound and capable of bearing the load imposed by
the manifold
•
Vertical - The flow gauges accuracy is impaired and the manual
air vents will be ineffective if the manifold is mounted on a
horizontal surface
•
The environment within which it is to be mounted should:
•
Be within the heated envelope of the building
•
Never drop below 2°C or rise above 60°C
•
In a dry location with non-condensing humidity levels
•
It is recommended that:
•
The manifold is mounted no less than 300mm above finished
floor level, to allow for easier installation and maintenance of
the manifold
•
A clearance of no less than 50mm is maintained on all sides for
future access
•
Any obstructions placed in front of it are removable to permit
future access
Step 1 -
Location Considerations