6.2 System Test Procedure
The following table describes the sequence associated with performing a system
test of the current configuration using the button panel interface.
LCD interface
Comments
SuperDuper 2-01
Status: Ready
Drives: 12345678
From the main window, press <menu> to
display the initial menu item.
Note: All drives have been activated.
1:System Test
Press <enter> to execute the system test
command.
Test System Drives
OK (enter/cancel)?
Press <enter> to acknowledge that you want to
proceed.
Testing Source
▓▓▓▓
Interim status of the system test of the source
drive.
Testing Target 1
▓▓▓▓
Interim status of the system test of the first
target drive.
. . .
Testing Target 8
▓▓▓▓▓▓▓▓
Interim status of the system test of the last
target drive.
Operation Complete
The status displayed after it completes the
command.
6.3 Clone Drive Procedure
The following table describes the normal sequence associated with performing a
clone operation of the source drive using the button panel interface.
LCD interface
Comments
SuperDuper 2-01
Status: Ready
Drives: 12345678
From the main window, press <menu> to
display the initial menu item.
1:System Test
Press < menu > again to advance to the next
menu item.
2:Clone Drive
Press <enter> to execute the clone drive
command.
3:Clone Drive
SHA Disabled
Wipe Enabled
Press <enter> to execute the clone drive
command with the SHA verify option disabled
and the wipe option enabled.
Clone Source Drive
OK (enter/cancel)?
Press <enter> to acknowledge that you want to
proceed.
Cloning 3.7GB/min
00:05:15 12GB/80GB
Interim status of the cloning operation.
Wiping 3.8GB/min
00:07:06 27GB/40GB
Interim status of the wiping to the end of the
target(s).
Operation Complete
The status displayed after it completes the
command.
13