Suitable Cable Size
Knockout Layer
Ø
2.5~4mm
Existing cable entry
Ø
5~6mm
Trim layer A
Ø
7~8mm
Trim layer A+B
Ø
11~12mm
Trim layer A+B+C
Ø
13~14mm
Trim layer A+B+C+D
Ø
15~15.5mm
Trim layer A+B+C+D+E
Installation Procedure
1. To install the detector, please drill a hole with diameter of 64~68mm on ceiling
board and keep the power cable outside. Please strip off 6 - 8mm of cable
sheathing for wiring (FIG.6).
2. Please refer to illustration of FIG.5 for correct wiring.
3. Insert the power module into the ceiling first, raise the two spring clips, and
insert the detector into the drilled hole on ceiling (FIG.7).
4. Detection range can be extended with additional slave sensors.
5. Restore the power supply.
Drill a hole with
=64~68mm on the
ceiling
=64~68
6 - 8mm
30 - 35mm
Power box
© Voltex Electrical 2018. All Rights Reserved.
®
FIG. 6
FIG. 7