8
Required water properties
The required water properties for the operation of
boiler and heating systems are specified in the "Stand-
ard values for water quality" chapter on page 11.
Commissioning
Note
Ensure that the installation room is well ventilated dur-
ing commissioning as there may be some odour nui-
sance.
Authorised to commission the boiler:
■
Viessmann Industrial Service (for contact details see
page 32) or
■
The system installer or
■
An approved contractor or institution nominated by
the system installer
Required for commissioning:
■
Presence of a competent expert authority
■
Completion of a
test report
■
Required signatories:
–
System builder
–
Regulatory expert
–
System user
■
The flue gas inspector (where applicable) should be
notified of the commissioning within 4 weeks
Recommended operating conditions to prevent
damage to the boiler system
Never interrupt boiler operation, even if no heat is
being drawn off temporarily
Maintain the following at all times
■
Water temperature: 70 °C
■
Specified operating pressure
Multi boiler systems with a boiler on permanent
standby:
Changeovers between heating and standby should be
infrequent, for example with each annual inspection of
the overall system.
Systems with operating temperatures
>
110 °C
Category IV boiler systems compliant with Pressure Equipment Directive
Requirements for commissioning
■
System installation has official approval.
■
The system has been checked by an expert author-
ity.
■
Commissioning of the control system is carried out
by a qualified organisation.
Requirements for operators
Only qualified personnel may operate, supervise and
service the system.
Requirements for operation without supervision
■
Boiler system is equipped in accordance with EN
12953, Part 6.
■
The system has received official approval for opera-
tion.
Checking system operation
Scope checks should be determined in accordance
with EN 12953-6
Shutdown and preservation
Shutdown
Shutdown means shutting down the system via the cir-
cuit breaker at the control panel. The duration of the
shutdown determines the preservation measures
described in this chapter.
A short-term shutdown is not recommended, as every
start-up process subjects the boiler to additional
stresses. For a period of up to 72 hours, for example
over a weekend, the boiler should be left to continue
operating.
Operating information
Operating tips
5673144
Operation