Boiler Lifting Instructions

 Lifting the Boiler

-   Connect spreader A to the crane hook.
-   Place the wire rope hooks on the lifting bars in 4 places  

 

on each side. Use a spreader, wire ropes and a crane  

 

with a minimum capacity of 7200 lb. (3625 kg).

-   Place pads between the boiler  and wire ropes so that  

 

the boiler will not be damaged.

-  Raise the arm of the crane to such an extent that the  

 

wire ropes become taunt. Make sure that the ropes  

 

are firmly hooked on the boiler body and at the chain  

 

block. If the ropes are not correctly hooked, slacken  

 

and rehook them.

-  After checking that the wire ropes are correctly  

 

hooked, operate the crane to lift the boiler.

It is essential to use appropriate lifting devices 

certified of lifting to a minimum of the boiler 

weight.

WARNING

If flue gas connection is damaged leakage may occur. 

Do not lift boiler at the flue gas connection.

The lifting should be performed by a trained technician. 

When lifting, take sufficient safety measures and proceed 

with great care. Refer to the lifting diagram. All lifting 

equipment is field supplied.

5786 833 - 03

Top view

Side view

Crane 

hook

Spreader A

Spreader A

Spreader B

Spreader B

Spreader B

Spreader B

Lifting bars

Lifting bars

Wire ropes

Wire ropes

Refer to the Installation Instructions applicable 

to this boiler.

Note:

 The boiler must beplaced on a foundation with a  

 

minimum height of 4 in. (100 mm).

Содержание Vitocrossal 300 CA3

Страница 1: ...experienced in the installation service and maintenance of hot water boilers There are no user serviceable parts on the boiler burner or control Ensure that main power to the equipment being serviced is off Ensure that the main fuel supply valve to the boiler is closed Take precautions to avoid accidental activation of power or fuel during service work for use with Vitocrossal 300 CA3 CA3B Unpacki...

Страница 2: ...welds shall have 100 magnetic particle inspection MPI 9 Shackle pins to be minimum 1 25 4 mm dia Structural steel 1 Structural steel shall conform to the latest edition of S16 09 and the CISC code of standard practice 2 Structural steel shall conform to CSA G40 21 300W G40 21M 350W class C for H S S and G40 21M 350W for W shape sections 3 All plates and round bars to be A44 300 MPa material minimu...

Страница 3: ...ropes are correctly hooked operate the crane to lift the boiler It is essential to use appropriate lifting devices certified of lifting to a minimum of the boiler weight WARNING If flue gas connection is damaged leakage may occur Do not lift boiler at the flue gas connection The lifting should be performed by a trained technician When lifting take sufficient safety measures and proceed with great ...

Страница 4: ... and recyclable paper Positioning boiler The boiler must be placed on a foundation A minimum height of 4 in 100 mm is required in order to allow for the condensate siphon connection Positioning the Boiler Boiler Lifting Instructions For more detail refer to the Installation Instructions applicable to this boiler ...

Отзывы: