Assembly
5777744-03 GB Subject to technical changes!
4.4 Assembling a mounting frame
(without floor)
NOTE
Damage due to improper mount-
ing!
f
Before drilling, make sure that any
moisture barriers which may be laid
on-site in screed are not damaged.
f
Make sure that no dowel holes
are under the cam locks of the ele-
ments.
f
Make sure that the sealing lip is
correctly seated on the floor on-site.
L
Thanks to their special design, the plastic U-profiles
seal all the way down to the floor after assembly.
Â
Screw U-profiles to floor of the installation space at
the intended position.
Â
Note the position of the door.
Â
Place wall elements into U-profiles.
Â
Rivet or screw wall elements with U-profiles.
Â
Make sure that the wall elements are perpendicular.
Door element without floor
L
Door element without floor is delivered with securing
for transportation and without door frame heating.
Â
Remove the door element’s securing for transport
before installation.
4.3
Level floor
4.3.1
Room with floor ventilation
L
Rooms with floor ventilation: Room temperature below
-5 °C.
Â
If the floor on site is not even or not horizontal, level
the height of the bottom ventilation panel:
with adjustment plates
Â
Lay bottom ventilation panel loosely at distances of
200–300 mm (clear space).
Â
Begin levelling at the highest point.
Â
Make sure that the element joints (
1
) are centred
during assembly and that the outsides of the ele-
ments (
2
) are lying with their full surfaces on the
bottom ventilation panels.
4.3.2
Room without floor ventilation
Â
If the floor on-site is uneven or not horizontal, adjust
its height with adjustment plates.