Installation
Dig a sufficiently wide and safe hole that is 1,415 m deep at the sewer’s lower edge.
1
Pipe the sewer from the building as close to the tank’s location as possible.
2
Use a soil compactor to compact a 20-cm level layer of sand bedding at the
bottom of the hole.
3
Carefully attach three-claw hoist grippers to the tank and use them to lift the
bio reactor into the hole. Use a spirit level to ensure that the bottom is level.
4
Fill the hole with sand, compacting the sand bedding every 20 cm or so
until mid-way up the bottom section. NB! Have the cover in place during
the installation to prevent sand getting in the tank.
5
Insert the sewer from the building through the seal in the tank’s side so that
at least 5 cm of the sewer pipe is visible inside the tank. Pipe the sewer outlet
from the tank to the discharge location.
6
Lift the riser on top of the tank well and attach it using the spikerpluggs
provided. Ensure that the riser’s seal stays in place during the installation.
7
NB! If the sewer is at a depth exceeding 700 mm, install a sufficient number of
concrete well rings between the bottom section and the riser. Seal the joint of
the well ring and bottom section using sealing strip. Drill new fastening holes
for the riser with a 8-mm concrete drill bit.
Connect the power cord to the socket. NB! Only a professional electrician
may carry out the connection. The riser has a ready-made penetration for
the electric cord.
Fill the hole with sand and install insulation panels on top of the sewers and
at the sides of the tank at a width of approximately 1 m. NB! The riser is
equipped with an installation level for the insulation plates.
Fill in the final soil, such as sand or earth, on top of the frost insulation.
Insert the air hose from the well into the blower’s connector.
Install the coarse filter to hang on the provided hook.
8
9
10
11
12
13
NB! Install the sewer’s ventilation above
the roof using the building’s internal
ventilating pipe. Do not use an inward
relief valve. If ventilation above the roof is
not possible, please contact customer
service before installation.
+