6 CHECKLIST FOR COMPLETED INSTALLATION
1. All items are unpacked and checked.
2. Proper clearances for service access have been maintained around the equipment.
3. Equipment is level and mounting fasteners are tight.
4. Piping completed to refrigerant loop.
5. All piping connections are leak-free.
6. Piping is routed to prevent chafing and rub-through.
7. System was evacuated and refrigerant charge and any necessary oil charge added.
8. Line voltage to power wiring matches equipment serial tag.
9. Power wiring connections completed including earth ground.
10. Power-line circuit breakers or fuses have proper ratings for equipment installed.
11. Control wire to condensing unit is shielded, connections completed, including shield wire
connected to earth (ground) at Liebert® units.
12. All wiring connections are tight.
13. Foreign materials have been removed from inside and around all equipment installed (shipping
materials, construction materials, tools, etc.)
14. Fan rotates freely.
15. Fan and compressor are rotating in the correct direction.
16. Blank start-up sheet included with the condensing unit is ready for completion by installer.
6 Checklist for Completed Installation
23
Содержание Liebert PFD
Страница 1: ...Liebert PFD Prop Fan Digital Condensing Unit Thermal Management Systems Installer User Guide...
Страница 4: ...Vertiv Liebert PFD Installer User Guide 4...
Страница 20: ...Vertiv Liebert PFD Installer User Guide 20 This page intentionally left blank...
Страница 24: ...Vertiv Liebert PFD Installer User Guide 24 This page intentionally left blank...
Страница 26: ...Vertiv Liebert PFD Installer User Guide 26 This page intentionally left blank...
Страница 34: ...Vertiv Liebert PFD Installer User Guide 34 This page intentionally left blank...
Страница 36: ...Vertiv Liebert PFD Installer User Guide 36 This page intentionally left blank...
Страница 47: ...Vertiv Liebert PFD Installer User Guide...