background image

Chapter 3    Commissioning            17 

NetSure 731 A41 Subrack Power System    User Manual 

The User and password of the M830B controller is set by web, see

 

NetSure™ Control Unit (NCU) User Manual Tabe 3-3    M830B 

controller paremeter settings 

Parameter 

Path 

Default settings 

Rated Capacity 

LCD/ Settings

Batt Settings

Charge

Batt1 Settings 

Rated Capacity 

300Ah 

LVD1 

LCD/ Settings

—LVD Settings—LVD1   

Enabled 

LVD2 

LCD/ Settings

—LVD Settings—LVD2   

Enabled 

LVD1 Voltage 

LCD/ Settings

—LVD Settings—LVD1Voltage 

44.0V 

LVD2 Voltage 

LCD/ Settings

—LVD Settings—LVD2Voltage 

43.2V 

AC Fail Required 

Web/Settings

—System—LVDGroup—AC Fail Required 

Enabled 

Num Batt Shunts 

LCD/ Settings

—Batt Settings—Basic Settings—Num 

Batt Shunts 

Shunt Current/ Shunt Voltage 

LCD/ Settings

—Batt Settings—Basic Settings—Batt1 

Settings

—Shunt Current/Shunt Voltage 

300A/25mV 

LVD Contactor Type 

Web /Settings

—LVD—LVD Contactor Type 

Bistable 

Walk-In 

LCD/ Settings

—Rect Settings—Walk-In 

Enabled 

Walk-In Time 

LCD/ Settings

—Rect Settings—Walk-In Time 

128S 

Note: The LVD2 voltage settings should follow battery factory's requirement and the battery capacity settings should 

based on the actual configuration settings. 

 

 

3.3   Alarm Check And System Operation Status Check 

 Alarm check 

Check that all functional unit can trigger alarms that can be displayed on the controller. 

 

OK 

Comment 

Pull out one rectifier. The ‘Rect N Com Failure’ alarm should be triggered. Insert the rectifier in. The alarm 
should disappear. Repeat the same procedures on other rectifiers 

 

 

Switch off battery MCB 1. The ‘Batt1 Failure’ alarm should be triggered. Switch on the MCB. The alarm 
should be cleared. Repeat the same on battery MCB 2 

 

 

Switch off a load MCB connected to a load route. The alarm ‘Load Fuse N Failure’ should be triggered. 
Switch on the MCB, and the alarm should be cleared. Repeat the same on the other load MCBs 

 

 

Remove all the battery MCBs. Keep only one rectifier in operation. Through the controller module, adjust 

the rectifier FC voltage to make it lower than the 

alarm point. The alarm ‘DC Voltage Low’ should be 

triggered 

 

 

Keep the rectifiers in operation. Set through the controller module the battery management parameter to 
‘Manual’. Enter the maintenance menu at the controller module. Select ‘Disconnect’ and confirm it. The 
battery protection contactor should be open, and the ‘BLVD’ alarm should be displayed at the controller 
module 

 

 

Note: when the preceding alarms are generated, the controller module will give alarms after approximately 

3s. 

 

 

 System operation status check 

There should be no alarms during normal system operation. The system operation status can be conducted through 

the controller module. 

 

OK 

Comments 

The system model is correct. 

 

 

The controller should display the correct AC voltage   

 

 

The controller should be able to display the DC voltage. The difference between the displayed voltage and 

that measured at the busbar should be less than 1

 

 

 

The controller should diaplay the battery current. The difference between the displayed and measured 

battery current should be less than 1

 

 

 

Check the number of the rectifier through the controller . The number should be consistent with the actual 

number. 

 

 

Check the voltage, current, current limiting point of rectifiers through the controller. They should agree with 

the actual parameter. 

 

 

For the system configured with temperature sensor, the controller should be able to diaplay the battery 

 

 

Содержание NetSure 731 A41-S1

Страница 1: ...Vertiv Tech provides customers with technical support Users may contact the nearest Vertiv local sales office or service center Copyright 2017 by Vertiv Tech Co Ltd All rights reserved The contents in...

Страница 2: ......

Страница 3: ...sonnel must be licensed to operate high voltage and AC power In operation the installation personnel are not allowed to wear conductive objects such as watches bracelets bangles rings When water or mo...

Страница 4: ...t be used In live operation keep the arm muscle tense so that when tool connection is loosened the free movement of the human body and tool is reduced to a minimum VI Dangerous energy Warning More tha...

Страница 5: ...y hand protective gloves should be worn to avoid injury by sharp object II Cable connection Notice Please verify the compliance of the cable and cable label with the actual installation prior to cable...

Страница 6: ......

Страница 7: ...5 3 1 Installation Check and Startup 15 3 2 Basic Settings 16 3 3 Alarm Check And System Operation Status Check 17 3 4 Final Steps 18 Chapter 4 Troubleshooting 19 4 1 Controller Alarms And Fault Handl...

Страница 8: ......

Страница 9: ...odule Take NetSure731A41 S1 for example the internal structure is shown as Figure 1 1 Positive terminal BatteryMCB Controller Rectifier AC input terminal N AC input terminal L Earthing screw AC output...

Страница 10: ...nternational standards such as CE NEBS and YD T983 Both the conducted and radiated interference reach Class B The rectifier safety design complies UL CE and NEBS The rectifier is of high power density...

Страница 11: ...inspection shall be done by representatives of both the user and Vertiv Tech Co Ltd To inspect the equipment you should open the packing case take out the packing list and check against the packing li...

Страница 12: ...name Connector specifications Wiring instruction AC power distribution AC input MCB H type terminal max cable CSA 50mm2 AC power line Grounding busbar One M8 bolt OT type wiring terminal max cable CSA...

Страница 13: ...system Figure 2 1 Cabinet and rack installation Installed in cabinet Insert the subrack power system to the matching cabinet as shown in Figure 2 2 Power subrack Figure 2 2 Installed in the cabinet sy...

Страница 14: ...e user requires the system to meet the CE certification install the epoxy board top cover to be installed at a distance of 1 8 meters high above the ground Epoxy board top cover for MFU unit cabling A...

Страница 15: ...erminals are shown in Figure 2 7 AC output terminal N Earthing screw AC output terminal L AC output terminal L AC output terminal N Figure 2 7 Illustration of the connection terminal Note 1 Recommende...

Страница 16: ...he positive battery cable to the DC positive bus bar 2 Connect copper lugs to the other end of the battery cables Bind the connecting parts with insulating tape and put them beside the battery Connect...

Страница 17: ...ttery protection and load disconnection alarm In the controller normal state the alarm contacts are always open when system issues above alarms related contacts will be closed All the status changes s...

Страница 18: ...is installed Dry contact 7 Exist when the second user interface board is installed Dry contact 8 Exist when the second user interface board is installed With default settings when the preceding alarm...

Страница 19: ...t used here 2 J2 is I2 C interface and provides the power See Table 2 6 for the dry contact terminal definition Table 1 1 Dry contact terminal definition Name of double layer port Pin No Pin name Defi...

Страница 20: ...y 8 3 DO7_COM Common contact of relay 7 4 DO8_COM Common contact of relay 8 5 DO7_NO NO contact of relay 7 6 DO8_NO NO contact of relay 8 The definition of dry contact function can be set through cont...

Страница 21: ...les 1 5 6 9 X1 X2 1 8 A X2 X1 X1 2 X1 3 X1 5 X2 3 X2 6 X2 5 Wiring table X1 X2 X1 2 X1 3 X1 5 X2 3 X2 6 X2 5 Colour White blue Green White green X1 9 6 5 1 X2 A 1 8 Figure 2 17 Communication signal ca...

Страница 22: ...14 Chapter 2 Installation Instruction NetSure 731 A41 Subrack Power System User Manual Temp terminal Figure 2 18 The position of temp terminal...

Страница 23: ...bles are connected to the controller module Check that the temperature sensor if any has been installed Startup preparations OK Comments Make sure that all the MCB are switched off and all the fuses a...

Страница 24: ...of the M225Scontroller Settings LVD1 default setting Yes Relay 2 settings Settings Relay 2 default setting LVD1 Setting LVD2 default 43 2V If the subrack system is used for outdoor default setting 45...

Страница 25: ...he alarm should be cleared Repeat the same on battery MCB 2 Switch off a load MCB connected to a load route The alarm Load Fuse N Failure should be triggered Switch on the MCB and the alarm should be...

Страница 26: ...to the equipment have been all removed Rehabilitate the power equipment and close the cabinet door Fill in the installation report and hand it over to the user Record all the operations in the file in...

Страница 27: ...r corresponding alarm For M225S controller Settings Clear For the submenu of Clear you can select Rect Lost to clear corresponding alarm The handling methods of normal alarms are given in Table 4 1 Ta...

Страница 28: ...bove the AC over voltage value the mains grid should be improved 11 Rect Fan Fails Pull out the rectifier to check if the fan is obstructed If yes clean it and push the rectifier back If the fan is no...

Страница 29: ...insert connection terminals to the corresponding J2 J6 and J7 respectively Make sure that the connections are fastened then push the controller into the system 5 Tighten the captive screw of the contr...

Страница 30: ...e the ambient temperature or remove the heat source Rect protection Current sharing imbalance Check whether the rectifier communication is normal If not check whether the communication cable is in nor...

Страница 31: ...rsonnel to disregard any alarms associated with this system while this procedure is performed 2 Loosen the captive screw on the module s handle Pull the handle down out from the module s front panel t...

Страница 32: ...not be easily disabled notify the appropriate personnel to disregard any alarms associated with this system while this procedure is performed 2 Remove the Rectifier from the shelf Refer to a previous...

Страница 33: ...ce the Rectifier into the shelf Refer to the previous procedure for step by step instructions 9 Enable the external alarms or notify appropriate personnel that this procedure is finished 10 Ensure tha...

Страница 34: ...point accuracy 1 Maximum efficiency 94 5 Noise peak peak rated output 200mV 0 20MHz Weighted noise rated output 2mV 300 3400Hz AC input alarm and protection AC input over voltage alarm point Default 2...

Страница 35: ...software at the host 1 Lock out at the first over voltage Once the output voltage reaches protection point the rectifier will shut off and hold that state It requires manual resetting to restore the...

Страница 36: ...to DC circuits 3 000Vac or 4 242Vdc for one minute leak curren 10mA without puncturing and electric arcing AC circuit to earth 50Hz 2 500Vac or 3 535Vdc for one minute leak curren 10mA without punctur...

Страница 37: ...2 Packing list of the battery rack Battery rack Accessory Two layer battery rack Four layer battery rack Accessory 1 2 4 Accessory 2 8 14 Accessory 3 2 4 Accessory 4 2 2 Accessory 5 0 2 Expansion bolt...

Страница 38: ...llation procedure of accessory 2 and accessory 4 2 Installation procedures of four layer battery rack 1 Install accessory 1 accessory 2 and accessory 3 according to Figure 2 a and Figure 2 b 2 Install...

Страница 39: ...y 4 Figure 5 Accessory Table 3 Packing list of the battery rack Accessory Accessory number Accessory 1 2 Accessory 2 6 Accessory 3 3 Accessory 4 2 Expansion bolt 4 pieces Fastener 1 set Installation p...

Страница 40: ...2 Figure 7 Installation procedure of accessory 2 and accessory 4 3 Fixing The Battery Rack 1 Fix the battery rack to the ground according to the installation dimensions shown in Figure 8 The fixing b...

Страница 41: ...fier 1 2 1 2 W80 8 PL QFA 1 SPD1 2 L 1 3 2 4 N L N 1 PE COM NC NO W80 7 J7 7 7 J7 8 W01 W01 31 J1 L 31 J2 L 31 J3 L 31 J4 L 3 2 2 N 2 W01 W01 N 2 31 J1 N 31 J2 N 32 J3 N 32 J4 N 1 4 3 4 31 W2493ZX1 2...

Страница 42: ...84 4 2 W80 9 BUS 1 X5 1 W80 8 QFD Front view 1 2 15 J7 W80 W06 7 31 7 46 18 J2 3 W84 W80 Front top view open the panel 2 J2 1 2 3 J1 1 7 39 7 41 12 1 12 2 8 PL 1 W84 W84 8 PL QFA 1 SPD1 2 QFA2 3 L1 1...

Страница 43: ...N CAN Controller M225S Positive Busbar 1 2 QFB1 1 2 1 2 QFD9 1 2 QFD8 1 2 QFD3 1 2 QFD2 1 2 QFD1 1 2 2 J2 1 2 3 J1 1 2 1 2 1 1 2 DC DC TEMP J6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10...

Страница 44: ...4 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 CAN CAN X5 1 J6 J3 J7 J5 J1 J2 J4 v v PE DCSPD 1 2 QFB1 1 2 X6 1 W2453X1 J6 2 1 J3 1 1 2 2...

Отзывы: