As you install hat channel the building frame will gain stiffness and strength. It is important that you check the frame  
sections with your level for plumb as you install each hat channel. You may want to clamp a corner diagonal brace to the 
frame at the front or back of the building on both sides to hold the first frame section square. Measure from the first frame 
section to get the remaining sections plumb.    
 

1. 

Install the first hat channel along the base rail starting on one side of the building at the corner. The bottom edge of the 

channel should be located 1” up from the bottom of the base rail. The hat channel should start at the corner of the build-
ing, 1” from the corner or centered on the corner post. Fasten the channel to the frame with #12 self-drilling screws, one 
in the top flange and one in the bottom flange at each vertical post.    

PAGE 19 

#12 SELF-
DRILLING SCREW 

MID CHANNEL DETAIL 

BASE RAIL 

HAT CHANNEL 

1” 

CORNER DETAIL 

1” 

2.  

Continue Hat Channel down the length of the building using 8’ lengths for 4’ on center frames, 10’ lengths for 5’ on 

center frames and 12’ lengths for 6’ on center frames. Butt the ends of the channels together and attach with screws as 
shown below. Your building may be of a length that requires you to use a 4’, 5’ or 6’ Hat Channel at one end of the build-
ing. If so, 4’, 5’ or 6’ channels are provided. 
 

All VersaTube buildings include framing for a Walk Door to be located on one side of the building

. Follow the in-

structions for framing around a Walk door opening in step 4. If you installed optional window frames, see step 5 for fram-
ing around window kit. 

Butt the ends of Hat Channels together, 
centered on a vertical post and fasten 
each hat channel end with 2 screws as 
shown. 

REMEMBER TO KEEP THE VERTICAL POSTS PLUMB AS YOU 

ATTACH HAT CHANNELS. 

3. 

Continue to install the remaining runs of hat channel on the sides of your building, referring to the chart on page 15 for 

height location. The dimensions on the chart are from the bottom of the base rail to the bottom edge on the lower hat 
channel flange. 
You will need to see steps 4 and 5 when you come to a door or window opening. 

STEP 9A: INSTALLING RAT TRACK HAT CHANNEL 

 

 
Rat Track is additional Hat Channel Girts that are installed on top of the collar tie to assist with longitudinal strength.  Rat 
track will be included with all buildings 30’ Wide or larger.  The rat track will start on the second frame and end on the second 
to last frame.  For 30’W, you will receive 3 runs of Hat Channel (40’W—4 runs; 50’W—5 runs, etc). Evenly space the hat 
channel on your collar tie and attach with (2) #12 x 3/4” self-drilling screws per connection

.

 

Содержание FBM3242410616-LT12

Страница 1: ...mplete satisfaction with your purchase In the unlikely event that there are any missing or damaged parts or if you simply need technical assistance please call our Toll Free Hot line at 1 800 900 7222...

Страница 2: ...r glasses when cutting metal or driving drilling screws NOTE The VersaTube Building System is an all domestically produced galvanized tubular steel framing system Maintenance is required twice annuall...

Страница 3: ...E 3 Chalk Line and Mason Line or Nylon String STRIKE WITH HAMMER Pencil Marker and Felt Marker Cordless 14 or 18 volt Or Electric Screw Gun With 5 16 Socket Drive Torque Setting One must be able to co...

Страница 4: ...ith 4 on center post spacing PEAK SIDE POST RAFTER HEIGHT EXTENSION T CONNECTOR L CONNECTOR COLLAR TIE BRACKET LEFT AND RIGHT 2X2 BACK FRONT BASE RAIL 2X2 VERTICAL EXTENSION 2X2 VERTICAL HEADER BRACE...

Страница 5: ...should be on 4 or 5 centers Measure the distance from the end pin on each base rail to the first pin on the next inserted base rail and adjust the joint so that all the pins are on 4 or 5 centers 46 o...

Страница 6: ...uld set the bottom dimension before you adjust and set the top dimension Now fasten the joints with 12 self drilling screws 4 screws in the peak to rafter and side post to rafter joints and 2 screws i...

Страница 7: ...2 self drilling screws Place screws on one side of the assembly as shown Note make sure the assembly is straight when you install screws Install a left and right Collar Tie Bracket on both ends as sho...

Страница 8: ...INSTALLING THE PEAK WEB BRACKET Measure up from both ends of the peak to find the center and make a mark Place a Web Bracket centered at your mark and pressed against the bottom of the peak Fasten th...

Страница 9: ...24 LONG ON ALL BUILDINGS Measure out 1 from the end of the Collar Tie and make a mark This will be the location of the upper Web Bracket for Web Brace 3 Attach the upper Web Bracket with 3 self drill...

Страница 10: ...st If adjustments must be made you can drive a wooden or metal stake into the ground about 8 from the building and use a Motor Cycle strap or Ratchet strap to pull the side post into plumb Place a cla...

Страница 11: ...square tubes The length is shown in the illustration below Join the Back Verticals and the appropriate Vertical Extensions do not install screws at this time Place the assemblies on the base rail pins...

Страница 12: ...r height is 7 you may have chosen to install a taller door Set the height at the bottom of your door header at 7 or the height of your chosen door Now install the vertical Header Brace in the center a...

Страница 13: ...1 3 4 WITH SWAGED REDUCED END 2 PLACES VERTICAL DOOR JAMB EXTENSION 8 GARAGE 2 X 3 X 30 3 4 10 GARAGE 2 X 3 X 54 3 4 12 GARAGE 2 X 3 X 78 3 4 2 PLACES VERTICAL HEADER BRACE 8 HIGH 2 X 2 X 25 10 HIGH 2...

Страница 14: ...ANGLE BRACKET 10 PLACES L CONNECTOR 2 PLACES BASE RAIL 2 X 2 X 35 3 4 2 PLACES BASE RAIL 2 X 2 X 29 3 4 VERTICAL DOOR JAMB 2 X 3 X 86 1 4 2 PLACES VERTICAL DOOR JAMB 2 X 3 X 81 3 4 WITH SWAGED REDUCED...

Страница 15: ...he bottom of the door header to the base rail and cut the 2 x 3 x 81 3 4 door vertical down to fit Set the vertical in place against the side of you door frame and attach it to the bottom of the heade...

Страница 16: ...er tubes and attach the door to the frame according to door manufactures instructions If you want to use screws provides by the door manufacturer you will have to drill pilot holes in the frame for th...

Страница 17: ...PAN HEAD SELF DRILLING SCREW BOTTOM WINDOW FRAME TUBE 42 60 OR ROUGH OPENING ANGLE BRACKET HORIZONTAL FRAME TUBE 2 x 3 x 45 3 4 Or 57 3 4 VERTICAL FRAME TUBE 2 X 3 X 60 OR CUT TO WINDOW ROUGH OPENING...

Страница 18: ...You can measure and locate each hat channel as you go or mark the locations of all the channels on the front and back frame sections and snap a chalk line the length of the building to mark the hat ch...

Страница 19: ...f a length that requires you to use a 4 5 or 6 Hat Channel at one end of the build ing If so 4 5 or 6 channels are provided All VersaTube buildings include framing for a Walk Door to be located on one...

Страница 20: ...hung door frame to the center of the next side post on that side of the door Cut addi tion pieces of hat channel as needed from 8 or 10 lengths to match up with the number of runs that intersect the d...

Страница 21: ...the outside of the other vertical nailer to the center of the second side post See illustration below Note On taller windows two runs of hat channel may cross the window PAGE 21 8 OR 10 CUT AN 8 OR 10...

Страница 22: ...is occurs on the front enclosure of the building you will use two Single Brackets overlapped Use 12 Self Drilling Screws to fasten brackets to the purlins girts or frame Use Pan Head Screws on the Sin...

Страница 23: ...MSMP INC 2 3 11 GIRTS ON BACK OF BUILDING ALL GIRTS ARE 1 1 2 SQUARE TUBE GIRT LENGTHS FOR 12 20 24 AND 30 WIDE BUILDINGS ON 12 WIDE BUILDINGS GIRTS ARE 67 3 4 LONG ON 20 WIDE BUILDINGS GIRTS ARE 56 3...

Страница 24: ...TS ON THE BACK OF THE BUILDING SEE HEIGHT CHART ON PAGE 23 If you install a taller garage door you will not need all of the center girts provided 12 WIDE BUILDINGS 11 3 4 LONG TYPICAL 52 3 4 LONG TYPI...

Страница 25: ...4 PLACES 94 3 4 LONG 4 PLACES 24 AND 30 WIDE BUILDINGS WITH 16 WIDE GARAGE DOOR All measurements are to the bottom of the girts 94 3 4 LONG ON 24 AND 30 WIDE BUILDINGS 8 SIDE HEIGHT 10 SIDE HEIGHT 12...

Страница 26: ...ING CONTINUED 24 AND 30 WIDE BUILDINGS WITH 2 9 WIDE GARAGE DOORS 52 3 4 LONG ON 24 AND 30 WIDE BUILDINGS 17 3 4 LONG ON 24 WIDE BUILDINGS 41 3 4 LONG ON 30 WIDE BUILDINGS 8 SIDE HEIGHT 10 SIDE HEIGHT...

Страница 27: ...e you cut the Top J Trim Attach the Side J Trim on both sides of the door to the vertical nailers with Pan Head Self Drilling Screws Clip two 1 long slits in the ends of the Top J Trim as shown below...

Страница 28: ...Trim to fit from the outside edge of the front flange on one side J Trim to the other The distance will be about 2 longer than the window frame Now clip two 1 long slits in both ends of the Top J Tri...

Страница 29: ...one 16 wide garage door you will be using 1 10 piece of Angle Trim and you will need to cut a 6 3 piece of Angle Trim The 6 3 trim will overlap the 10 piece 3 to trim out the under side of the door h...

Страница 30: ...e J Trim first at both ends and two additional places equally spaced from top to bottom with Pan Head Self Drilling Screws See illustration below for location of Side J Trim Place the Top J Trim on to...

Страница 31: ...on the building should come out flush with the other end of the building frame if the length is de visable by 3 If not example 20 or 25 long building you will need to trim the last panel to be flush w...

Страница 32: ...d insert the underlay edge of the next panel in that direction On 12 24 and 30 wide buildings the second back panel will also start in the center of the building with the overlap rib in the center of...

Страница 33: ...9 8 or 11 8 or 13 8 8 11 or 10 11 or 12 11 10 8 or 12 8 or 14 8 10 3 or 12 3 or 14 3 9 6 or 11 6 or 13 6 8 9 or 10 9 or 12 9 11 2 or 13 2 or 15 2 10 5 or 12 5 or 14 5 9 8 or 11 8 or 13 8 8 11 or 10 1...

Страница 34: ...lustration at lower right Attach the Eave Trim at the top of the side sheet metal all the way down both sides of the building with 12 x1 Painted Self Drilling Screws with Rubber washers Place the scre...

Страница 35: ...lk on it and give you location points for installing the remaining screws later when the purlins are not visible A third person will save time and energy with this step Place the overlap edge of the n...

Страница 36: ...s have been installed climb onto the roof Step only on flat areas next to frame sections or purlins Install the remaining screws use one screw next to each major rib Do not step on major ribs EAVE TRI...

Страница 37: ...lower edge of the gable trim should be flush with the lower edge of the roof panels Before you install the Gable Trim run a bead of Butyl Sealant down the major rib of the end roof panels Place the Bu...

Страница 38: ...e first piece of Ridge Cap on the peak at the back of the building Let the Ridge Cap overhang the Gable Trim by 1 2 Fasten with 1 Painted Self drilling Screws through the edge flange and into the top...

Страница 39: ...install the garage door Step 1 Track and Flag Brackets to Vertical Track Install mounting brackets and flag bracket to the vertical rails according to the manufacturer s instructions Step 2 Assemble D...

Страница 40: ...ngle together and drill two 5 16 hole through the door track using the two of the holes in the perforated angle as a guide See illustration Attach the extension angles to the door tracks with two 5 16...

Страница 41: ...ove the extension with a 5 16 x 3 4 hex bolt lock washer and nut Attach the brace to the rafter with a painted self drilling screw IF YOUR BUILDING HAS FRAME SECTIONS ON 4 CENTERS YOU WILL NOT NEED A...

Страница 42: ...o fit around the sides and top of your garage door Weather seal strips go on the door frame outside the door both sides and top of the door to seal out wind and rain Cut one seal to fit your door head...

Страница 43: ...he top of the first purlin or hat channel on the roof and also along the base rail or bottom side hat channel You may also want to place a couple of short strips of tape on the vertical frame tubes as...

Страница 44: ...WIDE BUILDING STEP 4 INSTALLING INSULATION ON THE ROOF Starting on one side of the roof at the same end of the building that you started the side panels Install double sided tape on top of the side i...

Страница 45: ...OWS 1 DIA 3 MINIMUM COMPRESSIVE STRENGTH OF CONCRETE AT 28 DAYS SHALL BE AS FOLLOWS 2500 PSI 4 PLACE REINFORCEMENTS AT MID THICKNESS FOR SLABS ON THE GROUND 5 ALL SPLICES IN CONTINUOUS REINFORCEMENT O...

Отзывы: