INSTALLATION
MANUAL
3- INSTALLATION
1
CHECK THAT THE POWER SUPPLY IS DISCONNECTED
Make sure that the power supply is disconnected at the charger point of installation.
2
CHECK THE CONNECTIONS
Check that the electrical wiring required to power the charger is available at the point
of installation.
OPTIONAL: If you are also going to install a CURVE device, check that the wiring for
the device is also available. For more information, see item 3.3 “INSTALLATION OF
THE CURVE DEVICE”.
OPTIONAL: If you are going to connect the charger to a single-phase or three-phase
meter, a communications device (modem, router, switch, ...) or to another charger,
check that the Ethernet wiring from that device is also available. For more information,
see item 3.4 “INSTALLATION OF THE SINGLE-PHASE AND THREE-PHASE METER SET”
and/or item 3.5 “CONNECTION OF THE CHARGER TO ANOTHER CHARGER, OR TO A
COMMUNICATIONS ELEMENT”.
INSTALLATION
3.1 INSTALLATION OF THE LITE ZERO/UNO/KUBO CHARGER
3
OPTIONAL: INSTALLATION OF THE STAND ELEMENT
If the installation of a STAND element is necessary to anchor the charger to the
ground, see item 3.2 “INSTALLATION OF THE STAND ELEMENT”.