IG-032-EN version 05; 18/06/2019
24
Installation
General instructions
pfu basic range: Prefabricated concrete
enclosure, ground-level walk-in type
Sloping ground
Carry out the excavation so the base platform is in a hard
area.
In these cases, it is essential that rainwater from the higher
ground be channelled, in order to prevent a gap from
forming under the building.
If there are any doubts concerning this subsequent
channelling, it is best to use a mixture of sand and cement
when levelling.
Once the boards are level, use the levelling board to check
that the ground is in perfect condition.
1
Concrete slab and levelling sand layer
2
Level 0
3
Landfill or plant matter
4
Hard ground
Figure 8.5.
Levelling specifications on sloping ground
Ground with a high water table
Proceed as follows when the water table level is high:
1. Establish the water table level
2. Only excavate the required depth, levelling as indicated
in the Normal Conditions and Sloping Ground sections.
1
Water table
Figure 8.6.
Levelling specifications on ground with a high water table