Installation Manual _________________________________________________________________
60 __________________________________________________________________ M210485EN-B
Assembling the Mast
Work Order
To assemble the mast, follow the work order below:
1.
Attach the 2-meter-high pedestal tube to the concrete
foundation.
2.
Lift the lower base of the mast to the upper end of the pedestal
tube and assemble the hinge axle.
3.
Attach the lifting rod to the clamp that is preinstalled to the
lowest mast tube.
4.
Attach the guy wires to the uppermost mast tube.
5.
Connect the mast tubes together.
6.
Lift the upper end of the mast on the tilting support.
7.
Assemble the holders to the lightning rod and attach the
assembly to the mast.
8.
Attach the winch and route the winch wire to the appropriate
guides.
9.
Install any other devices that will be installed to the tiltable part
of the mast and attach the cables to the mast with cable ties.
10.
Attach the jacketed copper grounding wire to the insulated guy
wire with the cable ties.
11.
Erect the mast with the winch and secure the hinge with the
bolts.
12.
Connect the guy wires with fasteners to their foundations and
mark them with the cable shrouds.
13.
Remove the winch and assemble the devices to the pedestal
tube.
For detailed instructions, refer to the following sections.