Side flue installations
• For installations where the air/flue
duct is to be installed to the side,
the position of the flue exit hole
can be determined as follows:
• Identify the correct measurement
as shown in fig. 4.3, carefully
measure the distance from the
bottom centre of the boiler
hanging bracket (centreline of the
two lower hanging bracket fixing
holes). This gives the position of
the centreline of the 127 mm flue
elbow and adaptor when
installed.
• The position of the flue exit hole
can be determined by carefully
levelling across the wall from this
mark.
• The position of the flue exit hole
should allow the flue to be
installed with an upwards slope
towards the terminal of
approximately 3° ± 1°, equivalent
to 50 mm ± 20 mm rise per metre
of flue length. Calculate the
required rise according to the flue
length and mark the position of
the flue exithole (fig 4.4).
Note: Due to the long lengths of flue
possible and the slope required, it
may be necessary to adjust the
location of the boiler installation
template. Please check that both the
boiler installation site and flue
termination are in accordance with
these instructions prior to drilling any
holes for the boiler hanging bracket.
• Once the position of the flue exit
hole has been determined, the
hole should be cut through the
wall using a core drill of 127 mm
diameter. The flue exit hole should
be cut with a rise towards outside
of 3°.
• Measure the distance from the
outside face of the wall to the
centre of the fan outlet on the
boiler (fig. 4.5).
This is dimension A.
• For installations where the
measured distance dimension A
(fig. 4.5) is greater than 960 mm,
an air/flue extension accessory
will be required. The number of
air/flue duct extensions which can
be used depends on the boiler.
Preparation
• Determine the installation site for
the boiler with reference to the
installation and servicing
instructions supplied with the
boiler.
• Ensure that all installation and
service clearances are available
and that the boiler flue can be
installed as detailed in these
instructions.
• Fix the paper template, supplied
with the boiler, to the wall
ensuring that the centreline of the
template is vertical using a
plumbline or spirit level.
*
Fig. 4.3
LAS Euro B/S 077/1
253
Fig. 4.4
LAS Euro B/S 083/1
INSTALLATION OF THE HORIZONTAL AIR/FLUE DUCT Ø 80/125 WITH
EXTENSIONS
*
= 190 mm ecoMAX combination and system boilers
*
= 176 mm ecoMAX pro and ecoTEC plus open vent
*
= 125 mm ecoTEC plus system & combination
*
*
= 253 mm ecoMAX
combination and system boilers
*
= 210 mm ecoMAX pro and ecoTEC plus
open vent
(from top holes on bracket)
*
= 238 mm ecoTEC plus
system & combination
IMPORTANT:
The air/flue duct is not concentric
and the air duct has a slope of 1.5°
(if the air flue duct is not cut). The
hole through the wall can therefore
be drilled horizontally with no slope.
Where extensions are used, these
must be installed with a slope at 3° ±
1° (equivalent to 50 mm ± 20 mm
rise per metre length) to ensure that
condensate dows not remain in the
sleeve.
834449_09GB_082006.qxd 10.08.2006 12:20 Seite 48
Supplied by HeatingSpares247.com
Содержание eco TEC plus 415
Страница 47: ...Installation and Servicing ecoTEC plus 47 Appendix 14 Supplied by HeatingSpares247 com...
Страница 48: ...Installation and Servicing ecoTEC plus 48 Supplied by HeatingSpares247 com...
Страница 49: ...Installation and Servicing ecoTEC plus 49 Supplied by HeatingSpares247 com...
Страница 50: ...Installation and Servicing ecoTEC plus 50 Notes Supplied by HeatingSpares247 com...
Страница 51: ...Installation and Servicing ecoTEC plus 51 Notes Supplied by HeatingSpares247 com...
Страница 52: ...0020020828_02 GB 08 2006 Subject to alteration Supplied by HeatingSpares247 com...
Страница 54: ...834449_09GB_082006 qxd 10 08 2006 12 20 Seite 2 Supplied by HeatingSpares247 com...
Страница 88: ...36 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 36 Supplied by HeatingSpares247 com...
Страница 112: ...60 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 60 Supplied by HeatingSpares247 com...
Страница 113: ...61 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 61 Supplied by HeatingSpares247 com...
Страница 114: ...62 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 62 Supplied by HeatingSpares247 com...
Страница 115: ...63 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 63 Supplied by HeatingSpares247 com...
Страница 116: ...834449_09 GB 082006 834449_09GB_082006 qxd 10 08 2006 12 20 Seite 64 Supplied by HeatingSpares247 com...
Страница 118: ...Supplied by HeatingSpares247 com...
Страница 120: ...0020010870 01 GB 03 2006 2 Supplied by HeatingSpares247 com...
Страница 138: ...0020010870 01 GB 03 2006 20 Supplied by HeatingSpares247 com...
Страница 158: ...Notes 0020010870 01 GB 03 2006 40 Supplied by HeatingSpares247 com...
Страница 159: ...Supplied by HeatingSpares247 com...
Страница 161: ...For the owner Instructions for use ecoTEC plus Wall hung open vent condensing boiler GB Supplied by HeatingSpares247 com...
Страница 171: ...Instructions for Use ecoTEC plus 11 Supplied by HeatingSpares247 com...
Страница 172: ...0020020829_02 GB 08 2006 Subject to alteration Supplied by HeatingSpares247 com...