INTRODUCTION 

This  manual  will  provide  the  information  to 
properly  install,  operate  and  maintain  the  valve 
to ensure a long service life.  The Figure 930 Air 
&  Vacuum  Valve  is  ruggedly  constructed  to 
provide  years  of  trouble-free  operation  with 
minimal maintenance.  
 
These Air & Vacuum Valves are not intended for 
use with fluids containing suspended solids such 
as  wastewater and  sewage.   The  GA  Industries 
Figure  935  or  939  Sewage  Service  Air  & 
Vacuum  Valves  are  recommended  for  such 
applications. 

 

CAUTION 

The  valve  is  NOT  recommended  for  use  with 
toxic  fluids,  fuels  or  fluids  containing  hazardous 
gases 
 
 
The  Shop  Order  (SO)  Number,  Figure  Number, 
size  and  pressure  rating  are  stamped  on  a 
nameplate attached to the valve.  Please refer to 
the SO number when ordering parts.  
 

DESCRIPTION OF OPERATION

 

The  Figure  930  allows  air  that  is  being  pushed 
ahead  of  the  incoming  fluid  to  escape  and 
ensure  a  complete  filling  of  the  pipeline  or 
vessel.    Once  the  air  has  been  exhausted  and 
the system is pressurized the valve closes tight.  
It  does  not  re-open  unless  and  until  the  system 
is  drained  and/or  a  negative  pressure  condition 
occurs within the pipe or vessel in order to admit 
air to minimize the vacuum condition. 
 
The  Figure  930  employs  the  Kinetic  aero-
dynamic  operating  principle  designed  to  ensure 
the  valve  is  not  prematurely  blown  shut  by  the 
high velocity exiting air. 
  

RECEIVING AND STORAGE 

Inspect  the  valve  upon  receipt  for  damage 
during  shipment.    Carefully  unload  all  valves  to 
the ground without dropping.  Do not pick up the 
valve by the “cowl.”  
 

 
The  valves  should  remain  in  a  clean,  dry  and 
weather  protected  area  until  installed.    For  long 
term storage (greater than 6 months) the rubber 
surfaces  of  the  seat  should  be  coated  with  a 
non-toxic  lubricant  such  as  "SuperLube"  made 
by  Synco  Chemical.    Do  not  expose  the  rubber 
parts to sunlight or ozone. 
 

INSTALLATION 

The  Figure  930  is  standard  with  NPT  inlet  and 
outlet  connections  in  sizes ½

” to 3” while the 4” 

is standard with ANSI Class 125 or 250 flanged 
inlet  and  NPT  outlet.    The  inlet  and  outlet 
connections  are  the  same  size.  Consult  the 
drawings  of  record  to  verify  the  configuration 
supplied and installed. 
 
The valve must be installed in an upright vertical 
orientation,  normally  at  a  high  point  in  the 
system. 
 
If  installed  outdoors,  below  ground  in  a  vault  or 
in an unheated area, adequate freeze protection 
must  be  provided.    Some  discharge  of  water 
may occur just prior to valve closure.  If installed 
indoors  or  in  a  vault,  the  valve  outlet  should  be 
directed to an adequate drain.  
 
An  isolating  valve  should  be  installed  between 
the valve and the pipeline or system to facilitate 
maintenance.    
 
Carefully  screw  threaded  end  valves  onto  pipe 
nipple using compatible thread sealant.  Tighten 
valve  using  wrench  flats.    DO  NOT  OVER-
TIGHTEN. 
 
Flat-faced  flanged  valves  should  be  mated  with 
flat-faced  flanges  and  full-face  gaskets.    If  ring 
gaskets  are  used  the  bolt  material  shall  be 
ASTM  A307  Grade  B  (or  equivalent).    Higher 
strength  bolting  should  only  be  used  with  full-
face gaskets.   

 

Lower  heavy  valves  using  slings  or  chains 
around  the  valve  body  and/or  the  lifting  eye.  
Lubricate  the  bolts  or  studs  and  insert  around 
flange.    Lightly  tighten  bolts  until  gaps  are 