19
3
Operation
3.1
Check before Power-on
Context
After installing the V-Power S14, users need to perform a pre-power check to ensure that the device
installation and cable connection are correct before performing the power-on operation.
Procedure
1
Check whether the V-Power S14 sequence is consistent with the layout diagram.
2
Check the cable connection on site.
Check whether the cables are connected correctly, whether the connectors are firm, and
whether the self-locking connector is tightly connected.
Check whether the communication cable and the power cable are separated.
3
Check whether the V-Power S14 are grounded.
4
Check the switch status.
The DC output switch of the V-Power S14 should be off.
The DC switch of the inverter should be off.
The circuit breaker from the inverter to the grid should be off.
3.2
Power-on