14
INSTALLING YOUR ROOM HEATER - continued
FREESTANDING INTERIOR VERTICAL INSTALLATION
1. Locate your Pellet Stove Room Heater in a location which meets the requirements of this manual, but in an area where
it does not interfere with the house framing, wiring, etc.
2. Install a non-combustible hearth pad underneath the pellet stove. This pad should extend at least 6” (152mm) in front
of the unit.
3. Place your Pellet Stove Room Heater on the hearth pad and locate the unit in a manner that will leave the exhaust vent
with a minimum of 3” (75mm) clearance to any combustible wall.
4. When installing the air intake, locate the center of the combustion air intake pipe at the back of your unit. Line up the
center with the same spot on your exterior wall and cut a 2-1/2” (64mm) diameter hole through the wall.
5. Secure all vent joint connections with 3 screws. Seal the exhaust vent joint connections with high temperature silicone
sealant.
6. Install the combustion air intake pipe.
7. Install a tee, with a cleanout, on the exhaust pipe found at the rear of your unit.
8. Install approved vent upward through the ceiling. When you pass through the combustible framing ensure that the ap-
propriate ceiling
fi
re stop is used. You must maintain a minimum 3” (75mm) clearance to combustibles and keep any
insulation away from the exhaust vent.
9. Extend the exhaust vent through the roof
fl
ashing and ensure that the vertical cap is approximately 36” (900mm) above
the roof.
Listed Termination
Flashing
36” (900 mm)
3” (75 mm) Clearance
to Combustibles
Use Ceiling Firestop
3” (75mm) Clearance
to Combustibles
3” (75 mm)
Tee with
Cleanout
6” (150 mm)
Combustion Air
Intake with approved cap
Non-Combustible
Floor Protection
Existing Combustible
Floor
Figure 10
6” (150 mm)
Use Ceiling Firestop
3” (75mm) Clearance
to Combustibles
Содержание 5660 (I)
Страница 25: ...25 VENT TERMINATION LOCATIONS Figure 22 ...