![Unipower UP2210 Скачать руководство пользователя страница 85](http://html1.mh-extra.com/html/unipower/up2210/up2210_installation-and-configuration-manual_3901853085.webp)
UNIPOWER
UP-2210R/P Hardware installation and configuration manual
85
2
Check the connection/wiring
2.1
Check nearby equipment (if possible) to ensure that the voltage, current and
power is equal to the measured values in the meter.
☐
2.2
Check vector diagram. The voltage phase sequence should be
U1 red (0°)
U2 green (-120°)
U3 blue (+120°)
☐
2.3
Check vector diagram. Each current should be /-90° from its
corresponding voltage
☐
2.4
Check that PF is >0.7 on all phases as well as total
☐
2.5
Check that P is positive for each phase (if not measuring on a generator)
☐
2.6
Check that unbalance is low (high value means wrong phase sequence)
☐
2.7
Select
transfer data
a few times. Cancel the transfer and verify that there isn’t a
continuous trigging of sag/swells or transients due to bad settings.
☐
2.8
Erase all old data in the meter
☐
The above points have been discussed:
Date: ____/____- ______
Installation performed by (Unipower representative): Unipower rep. contact information
__________________________________
______________________________
Installation performed by (customer):
__________________________________