background image

Safety

ESW 900 | Version 2.04

5

2.3 Requirements to staff

Qualifications

The different tasks described in this manual represent 
different requirements to the qualification of the persons 
entrusted with these tasks.

Only persons reliable working procedures can be ex-
pected from, are allowed to perform all works. Persons 
the responsiveness of which is affected by e. g. drugs, 
alcohol or medication, are not allowed to work with the 
machine.

The qualifications of the personnel for the different tasks 
are mentioned below:

Operator

The operator is instructed by the operating company 
about the assigned tasks and possible risks in case of 
improper behaviour. Any tasks which need to be per-
formed beyond the operation in the standard mode 
must only be performed by the operator if it is indicated 
in these instructions and if the operating company ex-
pressively commissioned the operator.

Qualified personnel

Due to their professional training, knowledge and expe-
rience as well as their knowledge of relevant regulations 
the specialist staff is able to perform the assigned tasks 
and to recognise and avoid any possible dangers them-
selves.

Manufacturer

Certain works may only be performed by specialist per-
sonnel of the manufacturer. Other personnel is not au-
thorized to perform these works. Please contact our cus-
tomer service for the execution of all arising work.

2.4 Personal protective equipment

The personal protective equipment serves to protect 
persons against impairments of safety and health while 
working. The staff member has to wear personal protec-
tive equipment while performing different tasks on and 
with the machine which are indicated in the individual 
paragraphs of these instructions.

The personal protective equipment is explained in the 
following paragraph:

WARNING!
Danger in case of insufficient qualification 

of the staff!

Insufficiently qualified persons cannot estimate the 
risks while using the wire rope hoist and expose 
themselves and others to the danger of severe or 
lethal injuries. 
-  Have all works only performed by qualified per-

sons.

-  Keep insufficiently qualified persons out of the 

working area. 

Head protection

The industrial helmet protects the head against fall-
ing objects and hitting on fixed objects.

Protective gloves

The protective gloves serve to protect the hands 
against sharp components as well as against fric-
tion, abrasions or deep injuries. 

Safety boots

Safety boots protect the feet from being crushed, fall-
ing parts and slipping over on slippery ground. 

Protective clothes

Protective clothes are made of a tightly fitted fabric 
without the protruding parts of low tear strength. 

Содержание ESW 900

Страница 1: ...ESW 900 ESW 900 Operating Instructions Electric Wire Rope Hoist ESW 900...

Страница 2: ...Customer service 3 1 3 Limitation of liability 3 2 Safety 3 2 1 Symbol explanation 3 2 2 Obligations of the operating company 4 2 3 Requirements to staff 5 2 4 Personal protective equipment 5 2 5 Gene...

Страница 3: ...e to develop our products even further 1 3 Limitation of liability All information and notes in these operating instructions were summarised while taking applicable standards and rules the state of th...

Страница 4: ...repared by her correspond to the current status of the regulations and must adapt these if necessary The operating company must unambiguously reg ulate and determine the responsibilities for instal la...

Страница 5: ...the manufacturer Other personnel is not au thorized to perform these works Please contact our cus tomer service for the execution of all arising work 2 4 Personal protective equipment The personal pro...

Страница 6: ...e requiring inspection For this reason the following guidelines issued by the trade association central office for accident prevention regarding steel cables used in lifting operations must be complie...

Страница 7: ...arrier or dealer 5 2 Packaging All used packaging materials and packaging aids are recyclable and should be taken to a materials recycling depot to be disposed of The delivery packaging is made of car...

Страница 8: ...e bottom onto an appropriate beam Step 3 Oil the cable before you use it for the first time Step 4 Connect the battery connection cable and the control panel with the connections of the wire rope hois...

Страница 9: ...l and the load may drop The wire rope hoist load hook should only be secured to suitable suspension points on the load Under no circumstances may a load be subjected to a heavy blow or collision ATTEN...

Страница 10: ...d undam aged condition Step 2 Check that the voltage of the voltage source is a 12 V direct current Step 3 Connect the crocodile clips to a 12 V battery The red cable with the positive pole and the bl...

Страница 11: ...rdance with the actual signs of wear Contact the manufacturer for further information concerning mainte nance tasks and intervals Please find the contact data on chapter 1 2 Customer service Step 1 Lu...

Страница 12: ...ge The cable guide should be checked when changing the cable and replaced if necessary Fig 5 Steel cable Maintenance intervals Maintenance tasks before each operation Check wire rope hoist for damage...

Страница 13: ...he hook part 1 Fig 7 Dimension of the hook part 2 Fig 8 Dimension of the hook part 3 Fig 9 Dimension of the hook part 4 According to DIN 15405 Part 1 the load hook should be replaced if it has widened...

Страница 14: ...and in the interest of the environment that all component parts of the ma chine are only disposed of in the intended and permit ted way 11 1 Decommissioning Immediately decommission disused machines i...

Страница 15: ...re on the type plate fixed to the electric wire rope hoist Example Load hooks for the electric wire rope hoist must be or dered Type of device Electric wire rope hoist ESW 900 Item number 6190900 Posi...

Страница 16: ...2 Spare parts drawing In case of service the following drawing shall help to identify the necessary spare parts If necessary send a copy of the parts drawing with the marked components to your author...

Страница 17: ...Spare parts ESW 900 Version 2 04 17 13 3 Electrical wiring diagram ESW 900 Fig 11 wiring diagram ESW 900...

Страница 18: ..._____ complies with all relevant provisions of the above mentioned directive as well as the other applied directives below including their applicable modifications at the time of the declaration EU di...

Страница 19: ...0 h As nec essary As nec essary As nec essary annu ally Function test coupling cleaning as necessary wear test coupling Measurement of wear Cable hook Replacement switch connection cable Replacement c...

Страница 20: ...www unicraft de...

Отзывы: