Unical TRISECAL 3P DUO Series Скачать руководство пользователя страница 32

32

COMMISSIONING AND OPERATION

The TRISECAL 3P boilers have been designed
to be used in sliding temperature to improve
the seasonal efficiency in all type of C.H.
systems.
When using the boiler at minimum output,
the smoke temperature can be extremaly
low, also below 160°C.
The turbulators will be pushed to the bottom
of the pipes, against the rear wall of the smoke

chamber.
Do not use automatic filling valves.
The commissioning of the burner must be
performed under the responsibility of a
specialized and well trained burner technician,
authorised by the burner manufacturer.
In that occasion a commissioning report has
to be filled out.

7.1 - PRELIMINARY CHECK

Once all the hydraulic, electrical and fuel
connections have been made, before starting
the boiler we suggest to ascertain that:
-

The expansion vessel and the pressure
relief valve are correctly connected and
are in no way interceptable.

-

The bulb of thermometer, working, high
limit and minimum thermostats are well
secured into their proper bulb holder.

-

The turbulators are correctly fitted in all
the smoke pipes.

-

The C.H. circuit has been washed and
rinsed and is free from solid impurities.

-

The C.H. circuit is filled with water and has
been completely purged.

-

The pumps operate properly.

-

The flow switch, the pressure relief valve,
and the overheating discharge valve, if
any, are adjusted at the right value.

-

The fuel, hydraulic, electricaI and safety
connections are executed in conformity
with national and local requirements in
force.

-

There are no water leaks.

-

The burner has been fitted according to
the instructions of the burner manufacturer.

-

The mains voltage and frequency are
compatible with the burner and the electrical

equipment of the boiler.

-

The burner is adjusted for the fuel type,
among those listed in the burner data plate,
available on the installation site, and the
burner output range is compatible with the
boiler output.

-

In the boiler house there are also the burner
instructions.

-

The C.H. pipes are properly insulated.

-

The C.H. system is capable to absorb the
heat quantity produced at the first start of
the burner, during the test period.

-

The shunt pump is installed as
prescribed in the paragraph 2.5.7.

7.2 - FIRST COMMISSIONING

At the commissioning stage of the boiler a
qualified technician has to perform the following
checks:
-

Internal and external sound test of burner
and fuel feeding pipe;

-

Adjustment of the fuel throughput according
to the nominal input of the boiler (it is
convenient to remember that the nominal
input can be adjusted between the minimum
and the maximum shown in the table of
pages 6 to 9), by sharing the output
between the 1st and the 2nd stage,
knowing that the 1st stage flame can go
down to the 60% of the nominal output
(which at its turn can vary between the
minimum and the maximum depending on
the output requested by the C.H. system).

Proceed, then, in the following way:
-

Open the fuel feeding cock and check that
there are no leaks in the feeding line.

-

Ascertain that all the switches of the
panel board are in OFF position and adjust
the working thermostat to the minimum

position.

-

Switch ON the panel board through the
main switch.

-

Switch ON the C.H. pump: it will start to
rotate as soon as the minimum water
temperature thermostat detects 50°C.

-

Switch the burner ON.

-

Position the working thermostats of 1st
and 2nd stages to the maximum setting
to create a heat request.

During this phase check that:
-

There are no smoke leaks from the front
door, the burner plate and the chimney
connection.

-

There is a draught at the chimney base
between 2 and 4 mm w.g.

-

There are no water leaks.

-

The different thermostats and the other
installation safety devices work properly.

-

The shunt pump operates correctly.

-

The burner ignition is good.

-

The burner characteristics (main
adjustments and nozzle type) correspond
to the boiler data plate.

With a burner properly adjusted it must be
possible to reach easily, from a smoke sample
taken at the chimney base, the values given
below:
1) With light oil having a maximum viscosity

of 1.5 °E at 20 °C:

   - CO

2

 = 12 to 13 %

   - Smoke index < 1
   - Smoke temperature = 190 to 210 °C
2) With Natural Gas:
   - CO

2

 = 9 to 10 %

   - Smoke temperature = 180 to 200 °C
(values related to a clean boiler, with water
at 70 °C).
It is suggested to adjust the fuel throughput
to the actual needs of the C.H. installation
without exceeding the a.m. smoke
temperatures and without going below 160 °C
with the boiler at maximum output.
The corrosion caused by acid condensation
of the combustion products is never
covered by the guarante, because it
depends only on the management of the
C.H. system.

7

Содержание TRISECAL 3P DUO Series

Страница 1: ...aaaaa 07 04 TRISECAL 3P TRISECAL 3P DUO INSTALLATION USE AND SERVICING INSTRUCTION to be kept by the user ...

Страница 2: ...e responsibility of the installer to fulfil all the regulations concerning the boiler house the safety devices the chimney the fuel supply lines the electrical installations and all the other local requirements and safety instructions Approvals The UNICAL boilers TRISECAL 3P range have been tested and CE certified for the gas operation by GASTEC ITALIA who has recognised to these boilers the confo...

Страница 3: ...page 21 3 2 Functions descriptions page 21 OPTIONAL PANEL BOARD WITH OUTER COMPENSATOR page 22 4 1 Functions description page 22 4 2 Panel board with outer compensator on request page 23 4 3 Electrical and hydraulic connections of C H page 24 4 4 Electrical and hydraulic connections of C H and D H W production circuit page 25 4 5 Outer compensator page 25 1 2 STANDARD PANEL BOARD FOR TS 3P DUO pag...

Страница 4: ...systems BS 5546 Installation of gas hot water supplies for domestic purposes 2nd Family Gases BS 6644 Ventilation for gas appliances of rated input exceeding 60 kW HEALTH SAFETY DOCUMENT No 635 The Electricity at Work Regulations 1989 The manufacturer s notes must NOT be taken in any way as overriding statutory obligations IMPORTANT These appliances are CE certificated for safety and performance I...

Страница 5: ...re equipped with a reversible hinged door which can be opened for this reason from L H or R H side The outer shell is insulated with a glass wool 1 2 WORKING PRINCIPLE The NOx formation process is strongly affected by the flame temperature the time during which the combustion gases stay in a high temperature zone oxygen partial pressure and its concentration The provisions to be adopted for the NO...

Страница 6: ...150 T4 ISO 7 1 Rp Rp T3 ISO 7 1 Rp1 Rp1 T1 T2 ISO 7 1 Rp1 Rp1 Weight with packaging kg 326 398 Maximum boiler working pressure bar 5 5 Smoke side pressure drop mm w c 3 5 5 5 5 7 5 Water side pressure drop m w c 0 04 0 06 0 05 0 07 Boiler water content l 131 187 Input min max kW 53 3 70 74 5 97 Output min max kW 50 65 70 90 740 740 A mm B mm 690 950 C mm 950 950 D mm 190 190 E mm 140 140 F mm 145 ...

Страница 7: ... 320 8 377 204 270 289 320 412 478 0 06 0 08 0 08 0 10 0 10 0 18 0 17 0 20 0 22 0 35 0 32 0 53 6 8 5 7 10 12 17 22 24 18 26 18 26 5 5 5 5 5 5 486 575 626 739 949 1118 DN 50 DN 50 DN 65 DN 65 DN 80 DN 80 Rp1 Rp1 Rp1 Rp1 Rp2 Rp2 Rp Rp Rp Rp Rp Rp 180 180 180 180 225 225 820 820 860 860 890 890 A mm 885 1145 1080 1210 1275 1470 B mm C mm 1082 1082 1182 1182 1352 1352 D mm 190 190 190 190 190 190 E mm...

Страница 8: ...O mm Hydraulic resistance for delta T 15K 210 210 TS 3P 450 TS 3P 600 TS 3P 450 TS 3P 600 2 1 TRISECAL 3P Type T6 Øi mm T5 Øi mm T4 ISO 7 1 T3 UNI 2278 PN16 T1 T2 UNI 2278 PN16 Weight with packaging kg Maximum boiler working pressure bar Smoke side pressure drop mm w c Water side pressure drop m w c Boiler water content l Input min max kW Output min max kW DN 100 DN 100 DN 65 DN 65 Rp1 Rp1 250 250...

Страница 9: ...erent models W mm B mm 1080 1210 1275 1470 1605 1800 A mm 1730 1730 1790 1790 1850 1850 Pressione max esercizio caldaia bar 5 5 5 5 5 5 Smoke side pressure drop mm w c 12 17 22 24 18 26 18 26 20 28 20 30 Water side pressure drop m w c 0 10 0 18 0 17 0 20 0 22 0 35 0 32 0 53 0 26 0 44 0 25 0 42 578 640 824 956 1416 1588 Boiler water content l Input min max kW 319 8 388 383 4 517 2 511 8 647 4 641 6...

Страница 10: ...and it should also comply with any relevant requirements of the local gas supplier local authority and the relevant Standard Codes of Practice and building regulations The boiler house must be ventilated through permanent openings having a total surface not lower than 1 30th of the floor area of the boiler house with a minimum of 0 5 m2 Ventilation by grilles communicating directly with the outsid...

Страница 11: ... of the boiler Among the inconvenients caused by the bad quality of the feeding water the most frequent and serious is the scaling of the heat exchange surfaces Less frequent but also dangerous is the corrosion of the water side surfaces of all the circuit It is well known that the lime due to its very low thermal conductivity reduces the heat transfer so that also a scaling of a few millimeters p...

Страница 12: ... the necessary water circulation through in any possible opening condition of the mixing valve and to guarantee therefore the respect of the minimum return temperature indicated This pump will be sized according to the following formula Q P x 22 where Q Water flow rate in liter h P Boiler nominal output in kW and the manometric head 1 2 m w c 2 6 FURNACE DOOR ADJUSTMENT OPENING CLOSING A special a...

Страница 13: ...ich a pressure test nipple 9 mm dia is fitted This can be used with a silicon pipe for the measurement of the counterpressure in the combustion chamber At the place of this pressure test nipple which must be held a special microbore pipe pos 2 will connect the flame sightglass directly to the pressure room downstream the fan of the burner The air blown by the fan will cool down and clean the sight...

Страница 14: ...with the panel board to the side panels 3 4 G Insert the thermometer and thermostat bulbs in the bulb holders as shown in fig 15 and connect the mains the burner the pump s and any ancillary equipment to the panel board Close the panel board Guide the burner plug through the side cable clamp plate 9 on the preferred side and clamp the cable using the cable clamp supplied Fix the side cable clamp p...

Страница 15: ...15 TRISECAL 3P 65 90 fig 14 fig 15 TRISECAL 3P 65 90 1 Thermometer bulb 2 Working thermostat bulb 3 Minimum thermostat bulb 4 Safety thermostat bulb 5 Bulb retaining clip ...

Страница 16: ...re removing the precut insulation follow the instructions supplied with the insulation it self E After removal of the two side screws from the panel board rotate its cover towards the front and insert the cables and the capillaries of thermometer and thermostats through the slots on its base Fit the panel board to front upper panel 10 Fit the upper panel 10 complete with the panel board to the sid...

Страница 17: ...cause the front insulation is suitable for two different boiler ranges TX N and TS 3P before removing the precut insulation follow the instructions supplied with the insulation it self H Fit the rear insulations pos 16 and 27 and fix the rear upper panel pos 26 I Position the panels 12 and 19 between the side upper panels pos 8 and 17 L After removal of the two side screws from the panel board rot...

Страница 18: ...18 TRISECAL 3P 450 600 fig 18 fig 19 TRISECAL 3P 450 600 1 Thermometer bulb 2 Working thermostat bulb 3 Minimum thermostat bulb 4 Safety thermostat bulb 5 Bulb retaining clip ...

Страница 19: ...rough the hole on the base of the panel board Fix the upper front panels to the upper sides panels of the casings of the two boilers Address the cables of the burners toward the plates fixed on the side panels in the external sides and stop them on the plates themselves with a cable clamp type PG 11 fit the burners plugs see wiring diagram on pages 28 and 30 The supply pumps and mixing valve cable...

Страница 20: ...e panel board terminal strip see wiring diagrams on figs 24 26 31 33 The seven pole plug and the cable must come out from the casing through the cable clamp plate pos 1 onto which the cable glande must be fixed fig 22 TRISECAL 3P DUO 360 1200 fig 21 1 Thermometer bulb boiler 1 2 Working thermostat bulb boiler 1 3 Minimum thermostat bulb boiler 1 4 Safety thermostat bulb boiler 1 5 Bulb retaining c...

Страница 21: ...e implies the observance of some foundamental rules as do not touch the appliance with wet or moist parts of the body or barefoot do not pull the electrical cables do not expose the appliance to the atmospheric agents rain sun etc do not allow the use of the boiler by untrained persons 3 2 FUNCTIONS DESCRIPTION Through the main switch 11 the panel board and the ancillary equipments connected to it...

Страница 22: ...k can also control two different heating zones provided convenient flow and return manifolds are available The automatic operation is made on the base of the data detected by the boiler and storage tank sensors the flow sensor to be fitted OPTIONAL PANEL BOARD WITH OUTER COMPENSATOR WIRING DIAGRAM TYPE 21108 for TS 3P 65 to 600 4 only when a mixing valve is there and the outer and room sensors The...

Страница 23: ...al F1 General fuse max 4A Ib Burner switch IG Illuminated main switch Ipi1 1st C H pump switch Ipi2 2nd C H pump switch Ipb D H W tank pump switch Pb D H W tank loading pump Pi1C H pump for direct zone Pi2C H pump for mixed zone Te Working thermostat 30 C 90 C Tm Minimum thermostat 30 C Ts High limit thermostat 100 C Vm2 Mixing valve for 2nd zone A Burner lockout warning lamp eventual B Hourmeter ...

Страница 24: ...gested to adopt a shunt pump Pr to guarantee the circulation through the boiler in any possible open condition of the mixing valve see fig 28 The shunt pump Pr which will have a throughput equal at least at 50 of the C H pump and a manometric of of 1 m W G will perform also an anticondensation function limiting the too cold returns into the boiler The hydraulic schemas shown in the figs 28 29 are ...

Страница 25: ...rameters which are not changeable and the parameters which are adjustable by the user according to his needs Standard System values Parameter Adjustment range 02 03 04 05 06 07 08 09 12 13 14 15 01 Outer temperature Temporary operation Nominal flow temperature circuit 1 Actual flow temperature circuit 1 Nominal flow temperature circuit 2 Actual flow temperature circuit 2 Nominal boiler temperature...

Страница 26: ...ump 3 Solar panel 10 C 90 C 2 C 20 C 0 1 Off On 0 1 Off On 0 1 Off On 0 1 Off On Parameter 1 3 80 45 5 0 5 1 0 1 1 10 FACTORY SET PARAMETERS protected by a secret code 51 Boiler maximum temperature 50 C 110 C 52 Boiler minimum temperature 10 C 60 C 53 Temperature increase for D H W 0 C 50 C 54 Simplified start 10 C 50 C 55 Activation of minimum temperature limit 0 1 Off On 56 Boiler temperature hy...

Страница 27: ...djustable The minimum thermostats accessible through the opening of the panel board cover switches OFF the C H pump during the reacing of the steady state and up to the obtention of 30 C within the boilers In case of three phase burner and or C H pump with a current higher than 3A convenient relays have to be foreseen between these ones and the panel board 11 Illuminated main switch 12 Burner swit...

Страница 28: ... C Te2 2 2nd stage working thermostat 2nd boiler 24 C 84 C Tm1 Minimum thermostat 1st boiler 30 C Tm2 Minimum thermostat 2nd boiler 30 C Ts1 High limit thermostat 1st boiler 100 C Ts2 High limit thermostat 2nd boiler 100 C A1 A2 Additional repetition of lockout for burners 1 2 B1 B2 Additional repetition of working hour meter for 1st stage for burners 1 2 C1 C2 Additional repetition of working hou...

Страница 29: ...o 1 and No 2 are optionals The mixing valve and the relevant motor are 6 2 PANEL BOARD WITH OUTER COMPENSATOR optional Note The outer compensator arrives to the customer with the manufacturer technical data already adjusted Asfarastheconnectioninstructionsanduse of the outer compensator are concerned please refer to the instruction manual supplied with the outer compensator As far as the programmi...

Страница 30: ... D H W tank pump switch Ipr Recirculating pump switch Pb D H W tank loading pump Pr Shunt pump P1 C H pump for direct zone P2 C H pump for mixed zone Te1 Working thermostat 1st boiler 30 C 90 C Te2 Working thermostat 2nd boiler 30 C 90 C Tm1 Minimum thermostat 1st boiler 30 C Tm2 Minimum thermostat 2nd boiler 30 C Ts1 High limit thermostat 1st boiler 100 C Ts2 High limit thermostat 2nd boiler 100 ...

Страница 31: ...ing valve see fig 35 The shunt pump Pr which will have a throughput equal at least at 50 of the C H pump and a manometric of of 1 m W G will perform also an anticondensation function limiting the too cold returns into the boiler The hydraulic schema shown in fig 35 are principle schema in case of different system circuits contact please our after sale service dept which will supply you with all th...

Страница 32: ...2 FIRSTCOMMISSIONING At the commissioning stage of the boiler a qualified technician has to perform the following checks Internal and external sound test of burner and fuel feeding pipe Adjustment of the fuel throughput according to the nominal input of the boiler it is convenient to remember that the nominal input can be adjusted between the minimum and the maximum shown in the table of pages 6 t...

Страница 33: ... of the water in the system At the end of the smoke circuit cleaning to the next restart check around the burner plate and the smoke chamber for smoke leaks In the case some smoke leaks were noticed first of all tighten the screws fitting the smoke and not getting result it will be necessary to replace the sealing gasket Similarly it will be necessary to act on the front door increasing at first t...

Страница 34: ...n the boiler to the ambient temperature Switch Off the electrical supply to the boiler and the burner Open the front door Remove the cleaning doors from the smoke chamber Shake and remove the turbulators fig 37 every 15 20 days of activity of the boiler to avoid that the residues of combustion can stop them so much to make difficult their removal Clean the turbulators and the smoke pipes fig 37 Tu...

Страница 35: ...ner needs air Accordingly wide openings are foreseen for the entry of the air in the boiler house These openings never have to be obstructed Maintain the boiler house clean and dust free The boiler is not a closet avoid to store any kind of materials Maintain the entry of the boiler free and easy to reach in any moment Ascertain that the boiler house is endowed with efficient emergency lamp ...

Страница 36: ...teldario Mantova ITALIA tel 39 0376 57001 r a telefax 39 0376 660556 This catalogue is purely indicative The manufacturers reserve the right to modify technical data and any other parts of the contents AG S P A ...

Отзывы: